10326-10328 N DEBRA AVE 91344
Certificate Information: 10326-10328 N DEBRA AVE 91344
- Application / Permit
- 22016-20000-11150
- Plan Check / Job No.
- B22VN05460
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 23'9" X 21' ATTACHED 2-CAR GARAGE INTO JUNIOR ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (e). REPLACE PORTION OF EXISTING EXTERIOR WALLS & ROOF RAMING PER PLAN. WORK DONE PER WFPP.
- Permit Issued
- Issued on 12/16/2022
- Issuing Office
- Current Status
- CofO Issued on 6/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 4/23/2022 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 4/26/2022 | APPLICANT |
| Applicant returned to address corrections | 11/18/2022 | HAYATO TSUCHIYA |
| Issued | 12/16/2022 | APPLICANT |
| CofO in Progress | 6/6/2025 | RAUL OLAGI |
| Permit Finaled | 6/10/2025 | RUBEN SALAS |
| CofO Issued | 6/10/2025 | RUBEN SALAS |
| Permit Finaled | 6/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/28/2022 | RIDWAN HARDY |
| Address approval | Cleared | 11/7/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 11/7/2022 | CHRIS CHAHBAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2022 | CHRIS CHAHBAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/25/2024 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/1/2024 | Partial Inspection | JOHN COLEMAN |
| Footing/Foundation/Slab | 5/10/2024 | Partial Inspection | JAVIER RAMOS JR |
| Underground Mechanical | 5/20/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 6/11/2024 | Partial Approval | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 6/11/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 6/11/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| PLUMBING-Rough | 6/11/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 6/18/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/18/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/18/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/18/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/17/2024 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Rough | 8/19/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Insulation | 8/19/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Drywall Nailing | 9/5/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Drywall Nailing | 9/18/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 9/18/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 9/24/2024 | Partial Approval | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 6/3/2025 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 6/6/2025 | Approved | RAUL OLAGI |
| Final | 6/6/2025 | OK to Issue CofO | RAUL OLAGI |
| Green Building Final | 6/6/2025 | Approved | RAUL OLAGI |
| Green Building Rough | 6/6/2025 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 6/6/2025 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 6/6/2025 | Approved | RAUL OLAGI |