9152 N INDEPENDENCE AVE 91311
Certificate Information: 9152 N INDEPENDENCE AVE 91311
- Application / Permit
- 22016-20000-11061
- Plan Check / Job No.
- B22VN05440
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- (ePlan) Structural only permit for new mechanical supports on an existing roof. (T.I. and Change of use from (E) warehouse to (N) agricultural use under the permit #22016-20000-08981)
- Permit Issued
- Issued on 8/22/2022
- Issuing Office
- Current Status
- Issued on 8/22/2022
Permit Application Status History
| Submitted | 4/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | YOUNG KIM |
| Corrections Issued | 5/10/2022 | YOUNG KIM |
| Quality Review Completed | 5/13/2022 | FARUK SEZER |
| Applicant returned to address corrections | 6/16/2022 | YOUNG KIM |
| Applicant returned to address corrections | 7/11/2022 | YOUNG KIM |
| Applicant returned to address corrections | 7/12/2022 | YOUNG KIM |
| Applicant returned to address corrections | 8/2/2022 | YOUNG KIM |
| Plan Check Approved | 8/16/2022 | YOUNG KIM |
| Issued | 8/22/2022 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Freitas,, Sean Patrick; Lic. No.: NA23563 | , |
| Contractor | Pnr Builders Inc; Lic. No.: 1028148-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/29/2022 | Partial Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 8/29/2022 | Partial Inspection | JEFFREY FULTON |
| Deputy Steel/Welding | 9/20/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 9/27/2022 | Conditional Approval | JEFFREY FULTON |
| Footing/Foundation/Slab | 9/30/2022 | Partial Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 11/7/2022 | Partial Approval | GRANT WOODS |
| Wood Frame | 11/7/2022 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 11/16/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 11/29/2022 | Partial Inspection | DEANDRE HOFFMAN |