2700 S MILITARY AVE 90064

Certificate Information: 2700 S MILITARY AVE 90064

Application / Permit
22016-20000-10952
Plan Check / Job No.
B22VN05391
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO 2-STORY S.F.D. TO THE (E) KITCHEN, (E) BATHROOM, AND TO REMOVE BEARING WAL IN (E) KITCHEN AND REMOVE NON-BEARING WALLS IN (E) BATHROOM. ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/3/2022
Issuing Office
Current Status
Permit Finaled on 12/16/2022

Permit Application Status History

Submitted 4/8/2022 APPLICANT
Assigned to Plan Check Engineer 4/11/2022 ALFRED RAMIREZ
Corrections Issued 4/11/2022 ALFRED RAMIREZ
Issued 5/3/2022 APPLICANT
Building Plans Picked Up 5/6/2022 APPLICANT
Permit Finaled 12/15/2022 JOHNNY MIRANDA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/20/2022 KIRK LINKLATER

Contact Information

Contractor Angel City Development Inc; Lic. No.: 1046204-B 20929 VENTURA BLVD #47496      WOODLAND HILLS, CA 91364
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/1/2022 Partial Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 7/27/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 8/8/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 8/8/2022 Partial Approval JOHNNY MIRANDA
Interior/Exterior Lathing 8/15/2022 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 8/25/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 8/25/2022 Approved JOHNNY MIRANDA
HVAC-Rough 8/25/2022 Approved JOHNNY MIRANDA
Insulation 8/30/2022 Approved JOHNNY MIRANDA
Drywall Nailing 9/2/2022 Approved EVAN COOPER
PLUMBING-Rough 9/2/2022 Corrections Issued EVAN COOPER
Shower Pan 9/15/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 9/16/2022 Approved JOHNNY MIRANDA
Final 12/15/2022 Permit Finaled JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 12/15/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 12/15/2022 Approved JOHNNY MIRANDA