7400-7402 N ASMAN AVE 91307
Certificate Information: 7400-7402 N ASMAN AVE 91307
- Application / Permit
- 22016-20000-10511
- Plan Check / Job No.
- B22VN05131
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) IN (E) SFD.
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Current Status
- CofO Issued on 2/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2022 | SERGIO MUNIZ |
| Corrections Issued | 4/6/2022 | SERGIO MUNIZ |
| Plan Check Approved | 4/26/2022 | SERGIO MUNIZ |
| Issued | 4/26/2022 | APPLICANT |
| Building Plans Picked Up | 4/27/2022 | APPLICANT |
| CofO in Progress | 12/14/2022 | CHRIS CHRISTENSEN |
| CofO Issued | 2/7/2023 | JOHN JANSON |
| Permit Finaled | 2/7/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 4/8/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/13/2022 | Approved | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 5/19/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 5/23/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 5/23/2022 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/23/2022 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2022 | Partial Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 6/23/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/23/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/30/2022 | Partial Approval | DAVID SANDOVAL |
| Green Building Rough | 6/30/2022 | Approved | DAVID SANDOVAL |
| Insulation | 7/8/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 7/12/2022 | Not Ready for Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 7/15/2022 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2022 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 7/21/2022 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 7/28/2022 | Approved | JESUS PINEDA |
| Shower Pan | 7/28/2022 | Approved | JESUS PINEDA |
| Final | 9/30/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 9/30/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 9/30/2022 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 9/30/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| Pre-Inspection | 10/18/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 11/9/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 11/9/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 11/9/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 11/9/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 12/13/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 12/13/2022 | Approved | CHRIS CHRISTENSEN |
| Special/Order Compliance | 12/13/2022 | Partial Inspection | JESUS PINEDA |