6950 N COSTELLO AVE 91405

Certificate Information: 6950 N COSTELLO AVE 91405

Application / Permit
22016-20000-10243
Plan Check / Job No.
B22VN04995
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: ADDITION AND CONVERT (E) RECREATION ROOM TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 6/15/2022
Issuing Office
Current Status
CofO Issued on 10/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2022 APPLICANT
Assigned to Plan Check Engineer 4/6/2022 DANIEL YIP
Corrections Issued 4/7/2022 DANIEL YIP
Plan Check Approved 6/14/2022 DANIEL YIP
Issued 6/15/2022 APPLICANT
CofO in Progress 10/27/2022 MICHAEL SMITH
CofO in Progress 10/27/2022 MICHAEL SMITH
CofO Issued 10/27/2022 MICHAEL SMITH
Permit Finaled 10/27/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/14/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/14/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/18/2022 CARLOS AGUILERA
Sewer availability Cleared 4/18/2022 CARLOS AGUILERA
Construction near power lines Cleared 6/10/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Hakhamaneshi,, Manouchehr; Lic. No.: C88083 12935 ALCOSTA BLVD   PO BOX 1435    SAN RAMON, CA 94583

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Final 6/23/2022 Not Ready for Inspection RICHARD DOCKUS
Pre-Inspection 6/23/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 6/23/2022 SGSOV Not Ready RICHARD DOCKUS
BUILDING-Rough-Frame 7/1/2022 Approved RICHARD DOCKUS
Drywall Nailing 7/1/2022 Approved RICHARD DOCKUS
Final 7/1/2022 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 7/1/2022 Approved RICHARD DOCKUS
Green Building Final 7/1/2022 Approved RICHARD DOCKUS
Green Building Rough 7/1/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 7/1/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 7/1/2022 Corrections Issued RICHARD DOCKUS
Final 7/14/2022 Corrections Issued JACK KARGODORIAN
Smoke Detectors 7/14/2022 Approved JACK KARGODORIAN
Final 9/7/2022 Corrections Issued JACK KARGODORIAN
Final 9/21/2022 Corrections Issued JACK KARGODORIAN
Final 10/14/2022 Conditional Approval ALAN MORELOS
Final 10/27/2022 OK to Issue CofO MICHAEL SMITH