1719 S WOOSTER ST 90035
Certificate Information: 1719 S WOOSTER ST 90035
- Application / Permit
- 22016-20000-10104
- Plan Check / Job No.
- B22VN04929
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 19'6" X 19' DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 2/15/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 4/7/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 4/12/2022 | APPLICANT |
| Applicant returned to address corrections | 8/30/2022 | JESSE ARELLANO |
| Plan Check Approved | 2/13/2023 | OMAR GARNICA |
| Issued | 2/15/2023 | APPLICANT |
| CofO in Progress | 6/7/2025 | MICHAEL PELHAM |
| Permit Finaled | 6/7/2025 | RICHARD STEINBACH |
| CofO Issued | 6/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 11/9/2022 | CINDY QI |
| Sewer availability | Cleared | 11/9/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2022 | CINDY QI |
| ZI | Cleared | 11/21/2022 | RYAN LY |
| Construction near power lines | Cleared | 1/21/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/14/2023 | Approved | JEREMY TODD |
| PLUMBING-Rough | 6/14/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Rough | 7/3/2023 | Approved | ARAM AVEDISIAN |
| Wood Frame | 7/3/2023 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 7/12/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/12/2023 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 7/19/2023 | Approved | ARAM AVEDISIAN |
| Special/Order Compliance | 8/10/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/21/2023 | Approved | MEL KHACHATOURIAN |
| Final | 12/21/2023 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 12/21/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 12/21/2023 | Approved | MEL KHACHATOURIAN |
| METHANE-Final | 12/21/2023 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 12/21/2023 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 12/21/2023 | Approved | MEL KHACHATOURIAN |
| Final | 6/20/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 6/20/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 6/20/2024 | SGSOV Approved | MEL KHACHATOURIAN |
| Final | 6/7/2025 | OK to Issue CofO | MICHAEL PELHAM |