723 W F ST 90744

Certificate Information: 723 W F ST 90744

Application / Permit
22016-20000-10024
Plan Check / Job No.
B22VN04888
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 5/19/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2022 APPLICANT
Assigned to Plan Check Engineer 4/5/2022 PINANK PATEL
Corrections Issued 4/5/2022 PINANK PATEL
Building Plans Picked Up 4/7/2022 APPLICANT
Applicant returned to address corrections 1/10/2023 ALFRED RAMIREZ
Applicant returned to address corrections 1/18/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 3/28/2023 RAMA DABADGE
Plan Check Approved 4/11/2023 JESSE ARELLANO
Issued 5/19/2023 APPLICANT
CofO in Progress 4/12/2024 EUGENE CASSIDY
Permit Finaled 4/12/2024 ANSON MAGLASANG
CofO Issued 4/12/2024 ANSON MAGLASANG
Permit Finaled 4/12/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 4/8/2022 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 4/8/2022 ERIK BEASLEY
Sewer availability Cleared 4/8/2022 ERIK BEASLEY
Construction near power lines Cleared 5/17/2022 RIDWAN HARDY
Construction within easement Cleared 5/17/2022 RIDWAN HARDY
Clean Up Green Up Cleared 7/20/2022 BRENNEN OBETO
ZA Case Cleared 7/20/2022 BRENNEN OBETO
ZI Cleared 7/20/2022 BRENNEN OBETO
Abandoned oil well Cleared 10/14/2022 LAVEON RIDER

Contact Information

Contractor A P American Construction Co; Lic. No.: 706560-B 7700 TOPANGA CANYON BLVD   UNIT 603    CANOGA PARK, CA 91304

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/14/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/2/2023 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 8/2/2023 Approved EUGENE CASSIDY
Green Building Rough 8/2/2023 Approved EUGENE CASSIDY
METHANE-Rough 8/2/2023 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 8/2/2023 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 8/2/2023 Approved EUGENE CASSIDY
Drywall Nailing 8/7/2023 Not Ready for Inspection JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 8/7/2023 Not Ready for Inspection JAMES CHAVEZ
Insulation 8/7/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 8/7/2023 Not Ready for Inspection JAMES CHAVEZ
BUILDING-Rough-Frame 8/9/2023 Approved EUGENE CASSIDY
Drywall Nailing 8/9/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 8/9/2023 Approved EUGENE CASSIDY
Shower Pan 8/9/2023 Approved EUGENE CASSIDY
Underground Mechanical 9/25/2023 Approved EUGENE CASSIDY
ELECTRICAL-Final 9/27/2023 Corrections Issued EUGENE CASSIDY
Gas Test 9/27/2023 Approved EUGENE CASSIDY
PLUMBING-Final 9/27/2023 Approved EUGENE CASSIDY
Final 9/29/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 9/29/2023 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/29/2023 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 9/29/2023 Approved EUGENE CASSIDY
ELECTRICAL-Final 3/27/2024 Approved EUGENE CASSIDY
Final 3/27/2024 OK to Issue CofO EUGENE CASSIDY
Green Building Final 3/27/2024 Approved EUGENE CASSIDY
HVAC-Final 3/27/2024 Approved EUGENE CASSIDY