6605 N WHITE OAK AVE 91335
Certificate Information: 6605 N WHITE OAK AVE 91335
- Application / Permit
- 22016-20000-09874
- Plan Check / Job No.
- B22VN04776
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 5/19/2022
- Issuing Office
- Current Status
- CofO Issued on 2/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | PINANK PATEL |
| Corrections Issued | 4/7/2022 | PINANK PATEL |
| Applicant returned to address corrections | 4/30/2022 | PINANK PATEL |
| Plan Check Approved | 5/18/2022 | PINANK PATEL |
| Issued | 5/19/2022 | APPLICANT |
| Building Plans Picked Up | 5/19/2022 | APPLICANT |
| CofO in Progress | 12/2/2022 | JEFFREY BULL |
| Permit Finaled | 2/18/2023 | DANIEL ORRANTE |
| CofO Issued | 2/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 4/14/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 4/19/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | 1 Stop Builders; Lic. No.: 1033108-B | 10117 SEPULVEDA BLVD STE 204 MISSION HILLS, CA 91345 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/13/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Footing/Foundation/Slab | 6/14/2022 | Approved | JEFFREY BULL |
| Underground Mechanical | 6/14/2022 | Partial Approval | JEFFREY BULL |
| BUILDING-Rough-Frame | 8/11/2022 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 8/11/2022 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2022 | Approved | JEFFREY BULL |
| Green Building Rough | 8/11/2022 | Approved | JEFFREY BULL |
| HVAC-Rough | 8/11/2022 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 8/11/2022 | Not Ready for Inspection | JEFFREY BULL |
| Gas Test | 8/15/2022 | Approved | JEFFREY BULL |
| Insulation | 8/15/2022 | Conditional Approval | JEFFREY BULL |
| Interior/Exterior Lathing | 8/15/2022 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 8/15/2022 | Approved | JEFFREY BULL |
| Shower Pan | 8/15/2022 | Not Ready for Inspection | JEFFREY BULL |
| Drywall Nailing | 8/25/2022 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 8/25/2022 | Approved | DAVID SANDOVAL |
| Sewer | 8/25/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Shower Pan | 8/25/2022 | Approved | DAVID SANDOVAL |
| Underground Mechanical | 8/25/2022 | Partial Approval | DAVID SANDOVAL |
| Drywall Nailing | 8/30/2022 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 8/30/2022 | SGSOV Not Ready | JEFFREY BULL |
| Sewer | 8/30/2022 | Approved | JEFFREY BULL |
| Underground Mechanical | 8/30/2022 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 10/19/2022 | Approved | JEFFREY BULL |
| Final | 10/19/2022 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 10/19/2022 | Approved | JEFFREY BULL |
| HVAC-Final | 10/19/2022 | Approved | JEFFREY BULL |
| PLUMBING-Final | 10/19/2022 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 10/19/2022 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 10/19/2022 | Approved | JEFFREY BULL |
| Final | 12/1/2022 | OK to Issue CofO | JEFFREY BULL |