19456 W NORDHOFF ST 91324
Certificate Information: 19456 W NORDHOFF ST 91324
- Application / Permit
- 22016-20000-09821
- Plan Check / Job No.
- B22VN04744
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Swimming Pool commercial
- Work Description
- TENANT IMPOROVEMENT TO CONVERT GYM TO INDOOR POOL
- Permit Issued
- Issued on 8/18/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 4/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | ERIC WONG |
| Corrections Issued | 4/16/2022 | ERIC WONG |
| Green Plans Picked Up | 4/18/2022 | APPLICANT |
| Quality Review Completed | 4/20/2022 | PETER KIM |
| Applicant returned to address corrections | 5/11/2022 | ERIC WONG |
| Plan Check Approved | 8/18/2022 | ERIC WONG |
| Issued | 8/18/2022 | APPLICANT |
| CofO in Progress | 10/31/2023 | DEANDRE HOFFMAN |
| Permit Finaled | 12/27/2023 | JEFFREY DURAN |
| CofO Issued | 12/27/2023 | JEFFREY DURAN |
| Permit Finaled | 12/27/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| Green Code | Cleared | 5/6/2022 | MICHAEL AYERS |
| DAS Clearance | Cleared | 5/19/2022 | ERIC WONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/22/2022 | DAGOVERTO GUERRERO |
| Fire Marshal Fire Life Safety | Cleared | 7/29/2022 | DOMINIQUE MEDINA |
Contact Information
| Architect | Wilkins,, Karen; Lic. No.: C27930 | 785 QUINTANA ROAD #180 MORRO BAY, CA 93442 |
| Contractor | M L Construction; Lic. No.: 962275-B | 6590 S RAINBOW BLVD #100 LAS VEGAS, NV 89118 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 8/31/2022 | Corrections Issued | JEFFREY FULTON |
| Light Gage Steel Frame | 11/3/2022 | Approved | CAMERON CHABAN |
| Drywall Nailing | 11/9/2022 | Partial Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 1/31/2023 | Approved | DEANDRE HOFFMAN |
| Special/Order Compliance | 8/25/2023 | Partial Inspection | JEFFREY FULTON |
| Final | 9/26/2023 | Corrections Issued | DEANDRE HOFFMAN |
| Green Building Final | 9/26/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Green Building Rough | 9/26/2023 | Approved | DEANDRE HOFFMAN |
| Reinforced Masonry Frame | 9/26/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 9/26/2023 | Approved | DEANDRE HOFFMAN |
| Special/Order Compliance | 9/27/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 10/4/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Green Building Final | 10/4/2023 | Approved | DEANDRE HOFFMAN |
| Reinforced Masonry Frame | 10/4/2023 | Approved | DEANDRE HOFFMAN |
| Final | 10/31/2023 | OK to Issue CofO | DEANDRE HOFFMAN |