695 S SANTA FE AVE 153 90021

Certificate Information: 695 S SANTA FE AVE 153 90021

Application / Permit
22016-20000-09805
Plan Check / Job No.
B22VN04736
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(27) Artist-in-Residence
Work Description
T. I. WITHIN A CURRENT RETAIL SPACE (1103 SF) INTO A NEW FITNESS CENTER WITH A NEW ADA RESTROOM. NFPA 13 FIRE SPRINKLERED.
Permit Issued
Issued on 8/30/2022
Issuing Office
Metro
Current Status
Issued on 8/30/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/30/2022 APPLICANT
Disabled Access Plans Picked Up 4/7/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 COLIN LOREDO
Corrections Issued 4/19/2022 COLIN LOREDO
Green Plans Picked Up 4/20/2022 APPLICANT
Quality Review Completed 4/22/2022 OMID HEDAYAT
Building Plans Picked Up 4/25/2022 APPLICANT
Applicant returned to address corrections 7/22/2022 COLIN LOREDO
Plan Check Approved 8/23/2022 SEAN SHAHMIRI
Issued 8/30/2022 APPLICANT

Permit Application Clearance Information

Green Code Cleared 5/17/2022 MICHAEL AYERS
Miscellaneous Cleared 6/3/2022 DANG NGUYEN
ZA Case Cleared 6/3/2022 DANG NGUYEN
ZA Case Cleared 6/3/2022 DANG NGUYEN
ZI Cleared 6/3/2022 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 6/13/2022 JEANIE LAM
ZI Cleared 6/14/2022 DAVID URITA
DAS Clearance Cleared 7/18/2022 COLIN LOREDO
Sewer availability Cleared 8/8/2022 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 1/6/2023 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 1/10/2023 Partial Approval RAFAEL CORTES
Insulation 1/18/2023 Approved ALFREDO LOPEZ
Light Gage Steel Frame 1/18/2023 Approved ALFREDO LOPEZ
Drywall Nailing 1/31/2023 Approved RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Partial Inspection JULIAN CAPUCETTI
SGSOV-Seismic Gas S/O Valve 4/6/2023 SGSOV Not Ready JULIAN CAPUCETTI
Pre-Inspection 4/7/2023 Approved JULIAN CAPUCETTI
Special/Order Compliance 4/29/2024 Partial Inspection RONALD JIMENEZ