18613-18615 W LEMARSH ST 91324

Certificate Information: 18613-18615 W LEMARSH ST 91324

Application / Permit
22016-20000-09689
Plan Check / Job No.
B22VN04692
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) '27-11" X 19' 2" IRR.-SHAPE ATTACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 7/26/2022
Issuing Office
Current Status
CofO Issued on 8/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 GURUNATH NESARAJAH
Corrections Issued 4/8/2022 GURUNATH NESARAJAH
Applicant returned to address corrections 7/14/2022 GURUNATH NESARAJAH
Plan Check Approved 7/25/2022 OMAR GARNICA
Issued 7/26/2022 APPLICANT
Building Plans Picked Up 8/1/2022 APPLICANT
CofO in Progress 8/11/2025 DAVID SCANTLIN
CofO Issued 8/18/2025 JOHN JANSON
Permit Finaled 8/18/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/25/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 5/25/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/1/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/24/2023 No Access for Inspection JOHN KIDWELL
Pre-Inspection 11/7/2023 Partial Inspection JOHN KIDWELL
PLUMBING-Rough 11/25/2024 Partial Approval KRISTEN CAUSEY
Deputy Drilled-In Anchors 12/9/2024 Conditional Approval KRISTEN CAUSEY
ELECTRICAL-Rough 12/23/2024 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 12/23/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 1/13/2025 Approved KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 1/29/2025 Approved KRISTEN CAUSEY
Green Building Rough 1/29/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 1/29/2025 Partial Approval KRISTEN CAUSEY
Insulation 3/24/2025 Conditional Approval KRISTEN CAUSEY
Drywall Nailing 4/1/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 6/5/2025 Approved KRISTEN CAUSEY
Shower Pan 6/5/2025 Approved KRISTEN CAUSEY
Final 8/5/2025 Corrections Issued DAVID SCANTLIN
Green Building Final 8/5/2025 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 8/5/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 8/5/2025 Approved DAVID SCANTLIN
Final 8/11/2025 OK to Issue CofO DAVID SCANTLIN
Green Building Final 8/11/2025 Approved DAVID SCANTLIN