900 W OLYMPIC BLVD 24th Floor 90015

Certificate Information: 900 W OLYMPIC BLVD 24th Floor 90015

Application / Permit
22016-20000-09546
Plan Check / Job No.
B22VN04647
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
ePlan Tenant improvement to (E) Restaurant on 24th floor
Permit Issued
Issued on 8/4/2022
Issuing Office
Current Status
Permit Finaled on 2/22/2023

Permit Application Status History

Submitted 4/12/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 HERNAN ARREOLA
Corrections Issued 5/1/2022 HERNAN ARREOLA
Quality Review Completed 5/10/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 8/3/2022 HERNAN ARREOLA
Issued 8/4/2022 APPLICANT
Permit Finaled 2/21/2023 KATY RAMIREZ

Permit Application Clearance Information

Redevelopment Project Area Cleared 5/23/2022 SUSAN WONG
Specific Plan Cleared 5/23/2022 PETE EYRE
Green Code Cleared 6/23/2022 HERNAN ARREOLA
DAS Clearance Cleared 6/30/2022 HERNAN ARREOLA
Food Service Establishment Cleared 7/18/2022 KENNETH BROWNE
Food establishment approval Cleared 7/27/2022 LACDHS APPROVED

Contact Information

Architect Carroll,, Rory James; Lic. No.: C35881 1000 BRANNAN STREET SUITE 404      SAN FRANCISCO, CA 94103
Contractor Lombardi Contracting Corporation; Lic. No.: 642036-B 7744 FORMULA PLACE      SAN DIEGO, CA 92121

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 10/3/2022 Partial Inspection KATY RAMIREZ
Insulation 10/12/2022 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 10/12/2022 Partial Approval TIMOTHY BUXTON
Deputy Steel/Welding 10/13/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 10/19/2022 Conditional Approval TIMOTHY BUXTON
Drywall Nailing 10/19/2022 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 10/19/2022 Partial Approval TIMOTHY BUXTON
Drywall Nailing 10/27/2022 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 10/27/2022 Approved TIMOTHY BUXTON
Drywall Nailing 11/2/2022 Partial Approval TIMOTHY BUXTON
Final 2/8/2023 Not Ready for Inspection KATY RAMIREZ
Green Building Final 2/8/2023 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 2/8/2023 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 2/8/2023 Approved KATY RAMIREZ
Final 2/16/2023 Not Ready for Inspection KATY RAMIREZ
Green Building Final 2/16/2023 Approved KATY RAMIREZ
Final 2/21/2023 Permit Finaled KATY RAMIREZ