901 3/4 E 49TH ST 90011
Certificate Information: 901 3/4 E 49TH ST 90011
- Application / Permit
- 22016-20000-09352
- Plan Check / Job No.
- B22VN04553
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Convert existing 3 car garage into new ADU lower level of a 3-unit apartment building at rear of lot.
- Permit Issued
- Issued on 2/9/2023
- Issuing Office
- Current Status
- Issued on 2/9/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2022 | JOE VO |
| Corrections Issued | 3/27/2022 | JOE VO |
| Plan Check Approved | 1/17/2023 | JOE VO |
| Issued | 2/9/2023 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 5/3/2022 | RICARDO BOHORQUEZ |
| Address approval | Cleared | 5/11/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 5/11/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Silva Design Construction Inc; Lic. No.: 956083-B | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/28/2023 | Conditional Approval | ALAN MORELOS |
| Footing/Foundation/Slab | 3/28/2023 | Not Ready for Inspection | ALAN MORELOS |
| Footing/Foundation/Slab | 3/29/2023 | Approved | ALAN MORELOS |
| Masonry Wall/Backfill | 3/29/2023 | Partial Inspection | ALAN MORELOS |
| Insulation | 6/2/2023 | Corrections Issued | RAFAEL CORTES |
| Pre-Inspection | 9/5/2025 | Not Ready for Inspection | ALFREDO LOPEZ |