901 3/4 E 49TH ST 90011

Certificate Information: 901 3/4 E 49TH ST 90011

Application / Permit
22016-20000-09352
Plan Check / Job No.
B22VN04553
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Convert existing 3 car garage into new ADU lower level of a 3-unit apartment building at rear of lot.
Permit Issued
Issued on 2/9/2023
Issuing Office
Current Status
Issued on 2/9/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/24/2022 APPLICANT
Assigned to Plan Check Engineer 3/25/2022 JOE VO
Corrections Issued 3/27/2022 JOE VO
Plan Check Approved 1/17/2023 JOE VO
Issued 2/9/2023 APPLICANT

Permit Application Clearance Information

Tenant Habitability Plan Cleared 5/3/2022 RICARDO BOHORQUEZ
Address approval Cleared 5/11/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 5/11/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 5/12/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Silva Design Construction Inc; Lic. No.: 956083-B       ,

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/28/2023 Conditional Approval ALAN MORELOS
Footing/Foundation/Slab 3/28/2023 Not Ready for Inspection ALAN MORELOS
Footing/Foundation/Slab 3/29/2023 Approved ALAN MORELOS
Masonry Wall/Backfill 3/29/2023 Partial Inspection ALAN MORELOS
Insulation 6/2/2023 Corrections Issued RAFAEL CORTES
Pre-Inspection 9/5/2025 Not Ready for Inspection ALFREDO LOPEZ