7045 N SHIRLEY AVE 91335
Certificate Information: 7045 N SHIRLEY AVE 91335
- Application / Permit
- 22016-20000-09305
- Plan Check / Job No.
- B22VN04518
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 18' 9" DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP & ENGINEERED DETAIL.
- Permit Issued
- Issued on 6/19/2022
- Issuing Office
- Current Status
- CofO Issued on 4/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 3/27/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 6/19/2022 | GURUNATH NESARAJAH |
| Issued | 6/19/2022 | APPLICANT |
| Building Plans Picked Up | 6/21/2022 | APPLICANT |
| CofO in Progress | 4/11/2023 | JEFFREY BULL |
| Permit Finaled | 4/14/2023 | JOHN JANSON |
| CofO Issued | 4/14/2023 | JOHN JANSON |
| Permit Finaled | 4/14/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/11/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/11/2022 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 6/4/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/4/2022 | RIDWAN HARDY |
| ZI | Cleared | 6/9/2022 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 8/25/2022 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 8/25/2022 | Partial Approval | DAVID SANDOVAL |
| Sewer | 8/25/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 9/8/2022 | Approved | JEFFREY BULL |
| Deputy Drilled-In Anchors | 9/15/2022 | Conditional Approval | JEFFREY BULL |
| Excavation/Setback/Form/Re-Bar | 9/16/2022 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 10/25/2022 | Approved | JEFFREY BULL |
| HVAC-Rough | 10/25/2022 | Approved | JEFFREY BULL |
| Insulation | 10/25/2022 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 10/25/2022 | Approved | JEFFREY BULL |
| Underground Mechanical | 10/25/2022 | Approved | JEFFREY BULL |
| Drywall Nailing | 11/4/2022 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 11/4/2022 | Approved | JEFFREY BULL |
| Shower Pan | 11/4/2022 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2022 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 3/9/2023 | Approved | JEFFREY BULL |
| Final | 3/9/2023 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 3/9/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 3/9/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 3/9/2023 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 3/9/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 4/7/2023 | Approved | JEFFREY BULL |
| Final | 4/7/2023 | OK to Issue CofO | JEFFREY BULL |
| HVAC-Final | 4/7/2023 | Approved | JEFFREY BULL |
| PLUMBING-Final | 4/7/2023 | Approved | JEFFREY BULL |