7311 1/2 W SUMMITROSE ST 91042

Certificate Information: 7311 1/2 W SUMMITROSE ST 91042

Application / Permit
22016-20000-09201
Plan Check / Job No.
B22VN04445
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Convert existing detached 18’x20’ two car garage to accessory dwelling unit (ADU)
Permit Issued
Issued on 5/17/2022
Issuing Office
Current Status
CofO Issued on 11/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2022 APPLICANT
Assigned to Plan Check Engineer 3/25/2022 ARSALAN SHABESTARI
Corrections Issued 3/25/2022 ARSALAN SHABESTARI
Plan Check Approved 5/17/2022 ARSALAN SHABESTARI
Issued 5/17/2022 APPLICANT
CofO in Progress 10/5/2023 WILLIAM WREN
CofO Issued 11/18/2023 RUBEN SALAS
Permit Finaled 11/18/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/11/2022 CHRIS CHAHBAZ
Sewer availability Cleared 4/11/2022 CHRIS CHAHBAZ
Eng Process Fee Ord 176,300 Cleared 4/21/2022 CHRIS CHAHBAZ

Contact Information

Architect Mehdizadeh,, Ali; Lic. No.: NA38086       ,
Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/8/2022 Partial Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 4/19/2023 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 4/19/2023 Corrections Issued WILLIAM WREN
PLUMBING-Rough 4/19/2023 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 6/9/2023 Conditional Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 6/20/2023 Approved WILLIAM WREN
Footing/Foundation/Slab 6/20/2023 Approved WILLIAM WREN
Underground Mechanical 6/20/2023 Partial Approval WILLIAM WREN
ELECTRICAL-Rough 7/21/2023 Corrections Issued DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 7/21/2023 Approved DAVID ANDERSON
PLUMBING-Rough 7/21/2023 Corrections Issued DAVID ANDERSON
ELECTRICAL-Rough 7/25/2023 Corrections Issued WILLIAM WREN
HVAC-Rough 7/25/2023 Approved WILLIAM WREN
PLUMBING-Rough 7/25/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 7/31/2023 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 7/31/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 8/4/2023 Approved WILLIAM WREN
Insulation 8/4/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 8/4/2023 Approved WILLIAM WREN
Drywall Nailing 8/14/2023 Approved WILLIAM WREN
ELECTRICAL-Final 9/12/2023 Not Ready for Inspection WILLIAM WREN
Final 9/12/2023 Corrections Issued WILLIAM WREN
HVAC-Final 9/12/2023 Not Ready for Inspection WILLIAM WREN
PLUMBING-Final 9/12/2023 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 9/12/2023 SGSOV Approved WILLIAM WREN
Smoke Detectors 9/12/2023 Approved WILLIAM WREN
ELECTRICAL-Final 9/18/2023 No Access for Inspection MICHEL ABAJAN
Final 9/18/2023 No Access for Inspection MICHEL ABAJAN
HVAC-Final 9/18/2023 No Access for Inspection MICHEL ABAJAN
Final 9/21/2023 OK to Issue CofO WILLIAM WREN