6918 N ENCINO AVE 91406

Certificate Information: 6918 N ENCINO AVE 91406

Application / Permit
22016-20000-09082
Plan Check / Job No.
B22VN04389
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 4/24/2022
Issuing Office
Current Status
CofO Issued on 7/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/22/2022 APPLICANT
Assigned to Plan Check Engineer 3/25/2022 PINANK PATEL
Corrections Issued 3/26/2022 PINANK PATEL
Plan Check Approved 4/24/2022 PINANK PATEL
Issued 4/24/2022 APPLICANT
Building Plans Picked Up 4/25/2022 APPLICANT
CofO in Progress 7/21/2023 JOHN KIDWELL
Permit Finaled 7/24/2023 JOHN JANSON
CofO Issued 7/24/2023 JOHN JANSON
Permit Finaled 7/24/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/2/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 4/2/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 4/4/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 9/22/2022 Approved JUSTIN HAWLEY
Deputy Drilled-In Anchors 9/27/2022 Conditional Approval KRISTEN CAUSEY
Footing/Foundation/Slab 9/28/2022 Not Ready for Inspection SEAN HAUPT
Excavation/Setback/Form/Re-Bar 10/3/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 10/3/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 11/4/2022 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 11/4/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Approved SEAN HAUPT
Green Building Rough 11/4/2022 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 11/4/2022 Approved SEAN HAUPT
PLUMBING-Rough 11/4/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 12/6/2022 Corrections Issued JON MCHUGH
Drywall Nailing 12/14/2022 Not Ready for Inspection JON MCHUGH
Interior/Exterior Lathing 12/14/2022 Approved JON MCHUGH
Drywall Nailing 12/28/2022 Approved JON MCHUGH
BUILDING-Rough-Frame 3/8/2023 Approved JON MCHUGH
Final 3/8/2023 Corrections Issued JON MCHUGH
Green Building Final 3/8/2023 Approved JON MCHUGH
Green Building Rough 3/8/2023 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 3/8/2023 SGSOV Not Ready JON MCHUGH
Smoke Detectors 3/8/2023 Corrections Issued JON MCHUGH
Final 3/29/2023 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 3/29/2023 SGSOV Not Ready JON MCHUGH
Smoke Detectors 3/29/2023 Approved JON MCHUGH
Final 3/31/2023 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 3/31/2023 SGSOV Approved JON MCHUGH
Final 7/18/2023 OK to Issue CofO JOHN KIDWELL