8019 S WESTLAWN AVE 90045
Certificate Information: 8019 S WESTLAWN AVE 90045
- Application / Permit
- 22016-20000-08886
- Plan Check / Job No.
- B22VN04281
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX. REC ROOM PORTION INTO ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(A) WITH EXTERIOR ACCESS STORAGE. REMOVE ATTACHED GARAGE PORTION. WORK PER ENGINEER. AUTOMATIC FIRE SPRINKLER REQUIRED.
- Permit Issued
- Issued on 9/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2022 | SERGIO MUNIZ |
| Corrections Issued | 3/26/2022 | SERGIO MUNIZ |
| Applicant returned to address corrections | 6/23/2022 | SERGIO MUNIZ |
| Applicant returned to address corrections | 7/2/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 7/6/2022 | APPLICANT |
| Plan Check Approved | 8/16/2022 | ROSENDO MEDINA |
| Issued | 9/13/2022 | APPLICANT |
| CofO in Progress | 5/24/2023 | BOBBY KEY |
| Permit Finaled | 5/31/2023 | DANIEL ORRANTE |
| CofO Issued | 5/31/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/31/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/7/2022 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 4/7/2022 | DINAH GARIN |
| Sewer availability | Cleared | 4/7/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2022 | DINAH GARIN |
| Specific Plan | Cleared | 4/18/2022 | VALERIA CEJA |
| Construction near power lines | Cleared | 6/3/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 3/29/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 3/29/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 3/29/2023 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/3/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 4/3/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 4/3/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 4/3/2023 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 4/4/2023 | Corrections Issued | BOBBY KEY |
| Insulation | 4/4/2023 | Corrections Issued | BOBBY KEY |
| Insulation | 4/6/2023 | No Access for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 4/14/2023 | Approved | BOBBY KEY |
| Wood Frame | 4/14/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2023 | Partial Approval | BOBBY KEY |
| Insulation | 4/19/2023 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 4/20/2023 | Approved | BOBBY KEY |
| Deputy Wood Construction | 4/20/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2023 | Approved | BOBBY KEY |
| Green Building Rough | 4/20/2023 | Approved | BOBBY KEY |
| Insulation | 4/20/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 4/20/2023 | Partial Approval | BOBBY KEY |
| Drywall Nailing | 4/24/2023 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 4/24/2023 | Approved | RICHARD STEINBACH |
| Shower Pan | 4/24/2023 | Approved | RICHARD STEINBACH |
| Gas Test | 5/4/2023 | Partial Approval | BOBBY KEY |
| Underground Mechanical | 5/4/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Final | 5/12/2023 | Approved | BOBBY KEY |
| Final | 5/12/2023 | Corrections Issued | BOBBY KEY |
| Gas Test | 5/12/2023 | Approved | BOBBY KEY |
| Green Building Final | 5/12/2023 | Approved | BOBBY KEY |
| HVAC-Final | 5/12/2023 | Corrections Issued | BOBBY KEY |
| METHANE-Final | 5/12/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 5/12/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/12/2023 | SGSOV Approved | BOBBY KEY |
| Service/Power Release | 5/12/2023 | Approved | BOBBY KEY |
| Smoke Detectors | 5/12/2023 | Approved | BOBBY KEY |
| Final | 5/24/2023 | OK to Issue CofO | BOBBY KEY |