10152 N OSO AVE 91311
Certificate Information: 10152 N OSO AVE 91311
- Application / Permit
- 22016-20000-08874
- Plan Check / Job No.
- B22VN04276
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE (E) 156 SQFT BREEZEWAY TO INCLUDE A BATHROOM AND UTILITY ROOM TO (E) SFD
- Permit Issued
- Issued on 5/2/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2022 | PETER MOSESIAN |
| Corrections Issued | 3/25/2022 | PETER MOSESIAN |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| Plan Check Approved | 4/19/2022 | PETER MOSESIAN |
| Issued | 5/2/2022 | APPLICANT |
| CofO in Progress | 10/12/2023 | DAVID SCANTLIN |
| Permit Finaled | 10/18/2023 | JOHN JANSON |
| CofO Issued | 10/18/2023 | JOHN JANSON |
| Permit Finaled | 10/18/2023 | JOHN JANSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Gemigniani,, Richard Louis; Lic. No.: C18783 | 4069 WOODCLIFF RD SHERMAN OAKS, CA 91403 |
| Contractor | Meuchel Steve Construction; Lic. No.: 795770-B | 10400 KEOKUK AVE CHATSWORTH, CA 91311 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/23/2022 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 5/31/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 2/17/2023 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 2/17/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 2/17/2023 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 2/17/2023 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 2/17/2023 | Corrections Issued | SEAN HAUPT |
| BUILDING-Rough-Frame | 3/8/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 3/8/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 3/8/2023 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 3/20/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 3/20/2023 | Approved | DAVID SCANTLIN |
| Insulation | 3/20/2023 | Approved | DAVID SCANTLIN |
| Shower Pan | 3/20/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 4/5/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 4/5/2023 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 4/5/2023 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 10/11/2023 | Approved | DAVID SCANTLIN |
| Final | 10/11/2023 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 10/11/2023 | Approved | DAVID SCANTLIN |
| HVAC-Final | 10/11/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 10/11/2023 | Approved | DAVID SCANTLIN |
| Smoke Detectors | 10/11/2023 | Approved | DAVID SCANTLIN |