18402 W ERWIN ST 91335

Certificate Information: 18402 W ERWIN ST 91335

Application / Permit
22016-20000-08872
Plan Check / Job No.
B22VN04274
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-0" X 20'-0" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/25/2022
Issuing Office
Valley
Current Status
Issued on 8/25/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/21/2022 APPLICANT
Assigned to Plan Check Engineer 3/25/2022 ARTIN ZARUKIAN
Corrections Issued 3/29/2022 ARTIN ZARUKIAN
Building Plans Picked Up 3/30/2022 APPLICANT
Applicant returned to address corrections 8/8/2022 OMAR GARNICA
Issued 8/25/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/4/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 4/4/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 4/5/2022 JOSE DUARTE-DIAZ
Construction near power lines Cleared 7/15/2022 WALTER RAMIREZ
ZI Cleared 8/10/2022 BRENNEN OBETO

Contact Information

Contractor Owner-Builder       ,
Engineer Ghavimi,, Rassoul Daneshvar; Lic. No.: C48282 7007 SHADETREE LANE      WEST HILLS, CA 91307

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/19/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 10/19/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 12/6/2022 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Rough 12/6/2022 Corrections Issued JON MCHUGH
Green Building Rough 12/6/2022 Not Ready for Inspection JON MCHUGH
HVAC-Rough 12/6/2022 Approved JON MCHUGH
PLUMBING-Rough 12/6/2022 Corrections Issued JON MCHUGH
BUILDING-Rough-Frame 12/27/2022 Corrections Issued JON MCHUGH
Green Building Rough 12/27/2022 Not Ready for Inspection JON MCHUGH
Rough-Elec/Plmb/HVAC 1/6/2023 Approved JON MCHUGH
Insulation 1/18/2023 Approved MORRIS JACKSON
BUILDING-Rough-Frame 1/26/2023 Conditional Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 1/26/2023 Conditional Approval JON MCHUGH
Green Building Rough 1/26/2023 Approved JON MCHUGH
Deputy Wood Construction 2/3/2023 Conditional Approval JON MCHUGH
BUILDING-Rough-Frame 2/10/2023 Approved SEAN HAUPT
Drywall Nailing 2/10/2023 Approved SEAN HAUPT
Interior/Exterior Lathing 3/9/2023 Approved SEAN HAUPT
Shower Pan 3/9/2023 Approved SEAN HAUPT
Special/Order Compliance 3/9/2023 Corrections Issued SEAN HAUPT