4949 1/2 N SYCAMORE TER 90042

Certificate Information: 4949 1/2 N SYCAMORE TER 90042

Application / Permit
22016-20000-08843
Plan Check / Job No.
B22VN04258
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Add 10'-4" x 18'-9" to and convert (e) 16-3" x 18'-9" detached garage into a (n) Accessory Dwellling Unit per CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 2/16/2023
Issuing Office
Current Status
CofO Issued on 7/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2022 APPLICANT
Assigned to Plan Check Engineer 3/25/2022 LUIS RINCON
Corrections Issued 3/26/2022 LUIS RINCON
Building Plans Picked Up 4/4/2022 APPLICANT
Plan Check Approved 10/27/2022 LUISANGEL VALENZUELA
Issued 2/16/2023 APPLICANT
CofO in Progress 7/5/2024 OSVALDO PARAMO
CofO Issued 7/9/2024 DEROLD HAUFF
Permit Finaled 7/9/2024 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 7/28/2022 KATIE DEBIASE
Miscellaneous Cleared 7/28/2022 KATIE DEBIASE
Address approval Cleared 8/1/2022 WALLIE JONG
Sewer availability Cleared 8/1/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/8/2022 WALLIE JONG

Contact Information

Architect Di, Zitti, Fernando; Lic. No.: C24587 21243 VENTURA BLVD #115      WOODLAND HILLS, CA 91364
Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/28/2023 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/20/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 3/28/2023 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/6/2023 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/14/2023 Approved OSVALDO PARAMO
Footing/Foundation/Slab 4/14/2023 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 5/30/2023 Approved OSVALDO PARAMO
ELECTRICAL-Rough 6/22/2023 Approved OSVALDO PARAMO
HVAC-Rough 6/22/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 7/6/2023 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Approved OSVALDO PARAMO
Green Building Rough 7/6/2023 Not Ready for Inspection OSVALDO PARAMO
Shower Pan 7/27/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 10/2/2023 Approved OSVALDO PARAMO
Green Building Rough 10/2/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 10/13/2023 Partial Approval OSVALDO PARAMO
Interior/Exterior Lathing 10/25/2023 Approved OSVALDO PARAMO
Sewer 11/2/2023 Approved ALIZAH MAYAGOITIA
Underground Mechanical 11/2/2023 Partial Approval ALIZAH MAYAGOITIA
Underground Mechanical 11/28/2023 Partial Approval OSVALDO PARAMO
Insulation 12/1/2023 Approved OSVALDO PARAMO
Drywall Nailing 12/8/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 2/23/2024 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 5/14/2024 Corrections Issued OSVALDO PARAMO
Gas Test 5/14/2024 Approved OSVALDO PARAMO
PLUMBING-Final 5/14/2024 Corrections Issued OSVALDO PARAMO
Service/Power Release 5/14/2024 Not Ready for Inspection OSVALDO PARAMO
Final 5/28/2024 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 5/28/2024 Approved OSVALDO PARAMO
Green Building Final 5/28/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/28/2024 SGSOV Approved OSVALDO PARAMO
Service/Power Release 5/28/2024 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 5/28/2024 Approved OSVALDO PARAMO
Final 6/12/2024 Partial Inspection OSVALDO PARAMO
Service/Power Release 6/12/2024 Approved OSVALDO PARAMO
Final 6/14/2024 OK to Issue CofO OSVALDO PARAMO