123 N HACKETT PL 90042
Certificate Information: 123 N HACKETT PL 90042
- Application / Permit
- 22016-20000-08835
- Plan Check / Job No.
- B22VN04254
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 33' X 30' 3" IRR.-SHAPE DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 2/16/2023
- Issuing Office
- Current Status
- CofO Issued on 7/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2022 | LUIS RINCON |
| Corrections Issued | 3/27/2022 | LUIS RINCON |
| Building Plans Picked Up | 4/4/2022 | APPLICANT |
| Plan Check Approved | 2/16/2023 | GURUNATH NESARAJAH |
| Issued | 2/16/2023 | APPLICANT |
| CofO in Progress | 7/5/2024 | OSVALDO PARAMO |
| CofO Issued | 7/9/2024 | DEROLD HAUFF |
| Permit Finaled | 7/9/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 4/8/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2022 | AMAAN MALIK |
| HPOZ | Cleared | 8/9/2022 | KATIE DEBIASE |
| ZI | Cleared | 8/9/2022 | KATIE DEBIASE |
Contact Information
| Architect | Di, Zitti, Fernando; Lic. No.: C24587 | 21243 VENTURA BLVD #115 WOODLAND HILLS, CA 91364 |
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/27/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Pre-Inspection | 2/28/2023 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 3/20/2023 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 3/28/2023 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 4/6/2023 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 4/14/2023 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 4/14/2023 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 5/30/2023 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/22/2023 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 6/22/2023 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 7/6/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2023 | Conditional Approval | OSVALDO PARAMO |
| Green Building Rough | 7/6/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Shower Pan | 7/27/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 9/20/2023 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/2/2023 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2023 | Approved | OSVALDO PARAMO |
| Green Building Rough | 10/2/2023 | Approved | OSVALDO PARAMO |
| Wood Frame | 10/2/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 10/13/2023 | Partial Approval | OSVALDO PARAMO |
| Interior/Exterior Lathing | 10/25/2023 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 11/3/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Underground Mechanical | 11/28/2023 | Partial Approval | OSVALDO PARAMO |
| Insulation | 12/1/2023 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 12/8/2023 | Approved | ALIZAH MAYAGOITIA |
| Sewer | 12/28/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 2/23/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Final | 5/14/2024 | Corrections Issued | OSVALDO PARAMO |
| Gas Test | 5/14/2024 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 5/14/2024 | Corrections Issued | OSVALDO PARAMO |
| Service/Power Release | 5/14/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 5/28/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 5/28/2024 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 5/28/2024 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 5/28/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Smoke Detectors | 5/28/2024 | Approved | OSVALDO PARAMO |
| Final | 6/12/2024 | Partial Inspection | OSVALDO PARAMO |
| Service/Power Release | 6/12/2024 | Approved | OSVALDO PARAMO |
| Final | 6/14/2024 | OK to Issue CofO | OSVALDO PARAMO |