4110 S BUCKINGHAM ROAD 90008

Certificate Information: 4110 S BUCKINGHAM ROAD 90008

Application / Permit
22016-20000-08823
Plan Check / Job No.
B22VN04248
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 22' X 17' 6" PORTION OF DETACHED GARAGE TO ACCESSORY DWELLING UNIT GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 6/24/2022
Issuing Office
Current Status
CofO Issued on 8/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2022 APPLICANT
Assigned to Plan Check Engineer 3/25/2022 GURUNATH NESARAJAH
Corrections Issued 3/26/2022 GURUNATH NESARAJAH
Applicant returned to address corrections 5/16/2022 GURUNATH NESARAJAH
Building Plans Picked Up 5/19/2022 APPLICANT
Plan Check Approved 6/19/2022 GURUNATH NESARAJAH
Issued 6/24/2022 APPLICANT
CofO in Progress 7/25/2023 ANTHONY EGSON
Permit Finaled 8/8/2023 DEROLD HAUFF
CofO Issued 8/8/2023 DEROLD HAUFF
Permit Finaled 8/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/1/2022 KIRK LINKLATER
Address approval Cleared 4/2/2022 JEANETTE VONG
Sewer availability Cleared 4/2/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 5/10/2022 JEANETTE VONG
Specific Plan Cleared 6/2/2022 KYLE WINSTON

Contact Information

Contractor Lefert Maintenance Group Inc; Lic. No.: 1051028-B 3325 WILSHIRE BOULEVARD #350      LOS ANGELES, CA 90010
Engineer Manlangit,, Vicente Balingasa; Lic. No.: C75499 7919 SAUSALITO AVE      WEST HILLS, CA 91304

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/26/2022 Approved ANTHONY EGSON
Sewer 10/26/2022 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 10/31/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 10/31/2022 Approved ANTHONY EGSON
Footing/Foundation/Slab 11/4/2022 Approved ANTHONY EGSON
Deputy Drilled-In Anchors 11/9/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 11/14/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 11/14/2022 No Access for Inspection ANTHONY EGSON
Green Building Rough 11/14/2022 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 11/14/2022 No Access for Inspection ANTHONY EGSON
PLUMBING-Rough 11/14/2022 No Access for Inspection ANTHONY EGSON
Deputy Wood Construction 11/17/2022 Approved ANTHONY EGSON
PLUMBING-Rough 11/18/2022 Partial Approval ANTHONY EGSON
Rough-Elec/Plmb/HVAC 11/18/2022 Approved ANTHONY EGSON
Sewer 11/18/2022 Not Ready for Inspection ANTHONY EGSON
Underground Mechanical 11/18/2022 Partial Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Off-Hour Fees Due
Gas Test 11/22/2022 Off-Hour Fees Due
Sewer 11/22/2022 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Off-Hour Fees Due
Gas Test 11/23/2022 Approved HORACE FULTZ
Gas Test 11/23/2022 Off-Hour Fees Due
Sewer 11/23/2022 Approved HORACE FULTZ
Sewer 11/23/2022 Off-Hour Fees Due
Insulation 11/28/2022 Corrections Issued ANTHONY EGSON
Interior/Exterior Lathing 11/28/2022 Approved ANTHONY EGSON
Shower Pan 11/28/2022 Approved ANTHONY EGSON
Insulation 12/1/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 12/1/2022 Approved ANTHONY EGSON
Drywall Nailing 12/7/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 4/13/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 4/13/2023 Corrections Issued ANTHONY EGSON
Final 4/13/2023 Corrections Issued ANTHONY EGSON
Green Building Final 4/13/2023 Approved ANTHONY EGSON
Green Building Rough 4/13/2023 Approved ANTHONY EGSON
HVAC-Final 4/13/2023 Corrections Issued ANTHONY EGSON
PLUMBING-Final 4/13/2023 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 4/13/2023 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 4/13/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 4/26/2023 Not Ready for Inspection ANTHONY EGSON
Final 4/26/2023 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 4/26/2023 Approved ANTHONY EGSON
PLUMBING-Final 4/26/2023 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 4/26/2023 SGSOV Approved ANTHONY EGSON
Final 5/24/2023 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 7/3/2023 Corrections Issued ANTHONY EGSON
Final 7/3/2023 Corrections Issued ANTHONY EGSON
Final 7/25/2023 OK to Issue CofO ANTHONY EGSON