11559-11561 N WOODLEY AVE 91344

Certificate Information: 11559-11561 N WOODLEY AVE 91344

Application / Permit
22016-20000-08668
Plan Check / Job No.
B22VN04175
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan ADU conversion. Convert existing attached 2 car garage(19'x22') to Accessory Dwelling Unit PER STATE LAW
Permit Issued
Issued on 4/8/2022
Issuing Office
Current Status
CofO Issued on 1/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2022 APPLICANT
Assigned to Plan Check Engineer 3/21/2022 CARLOS MONTES
Corrections Issued 3/21/2022 CARLOS MONTES
Plan Check Approved 3/26/2022 CARLOS MONTES
Issued 4/8/2022 APPLICANT
CofO in Progress 12/3/2024 JAVIER RAMOS JR
No Progress 12/12/2024 ROBERT GOLD
CofO in Progress 12/12/2024 ROBERT GOLD
No Progress 1/2/2025 RUBEN SALAS
CofO in Progress 1/2/2025 RUBEN SALAS
Permit Finaled 1/2/2025 RUBEN SALAS
CofO Issued 1/2/2025 RUBEN SALAS
Permit Finaled 1/2/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/23/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/23/2022 LEE GUILBEAUX
Sewer availability Cleared 3/23/2022 LEE GUILBEAUX
ZA Case Cleared 3/24/2022 RYAN LY

Contact Information

Architect Kim,, Hoejun; Lic. No.: NA37047       ,
Contractor Smart Construction And Plumbing; Lic. No.: 994517-B 1124 SOUTH ARDMORE AVENUE      LOS ANGELES, CA 90006
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/6/2022 Partial Approval JAVIER RAMOS JR
Sewer 6/6/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/24/2022 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 6/24/2022 Approved JAVIER RAMOS JR
Green Building Rough 6/24/2022 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 6/24/2022 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 6/30/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/30/2022 Approved JAVIER RAMOS JR
Green Building Rough 6/30/2022 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 6/30/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 6/30/2022 Partial Approval JAVIER RAMOS JR
Drywall Nailing 7/7/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 7/7/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 7/7/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Drywall Nailing 7/14/2022 Approved DEANDRE HOFFMAN
Insulation 7/14/2022 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 7/14/2022 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 8/5/2022 Corrections Issued JAVIER RAMOS JR
Final 8/5/2022 Corrections Issued JAVIER RAMOS JR
Gas Test 8/5/2022 Corrections Issued JAVIER RAMOS JR
HVAC-Final 8/5/2022 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 8/5/2022 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Final 8/19/2022 Approved JAVIER RAMOS JR
Final 8/19/2022 Corrections Issued JAVIER RAMOS JR
Gas Test 8/19/2022 Approved JAVIER RAMOS JR
HVAC-Final 8/19/2022 Approved JAVIER RAMOS JR
PLUMBING-Final 8/19/2022 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/19/2022 SGSOV Approved JAVIER RAMOS JR
Green Building Final 10/16/2024 Approved JAVIER RAMOS JR
Green Building Rough 10/16/2024 Approved JAVIER RAMOS JR
Smoke Detectors 10/16/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 12/3/2024 Approved JAVIER RAMOS JR
Final 12/3/2024 OK to Issue CofO JAVIER RAMOS JR
Special/Order Compliance 12/18/2024 Corrections Issued JAVIER RAMOS JR