9047-9049 N TERHUNE AVE 91352
Certificate Information: 9047-9049 N TERHUNE AVE 91352
- Application / Permit
- 22016-20000-08386
- Plan Check / Job No.
- B22VN04032
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 22'-11" X 19' ATTACHED GARAGE AND 10'-10" X 15' IRREG SHAPED PORTION OF SINGLE FAMILY DWELLING TO ACCESSORY DWELLING UNIT (562 SQ FT) PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 5/13/2022
- Issuing Office
- Current Status
- CofO Issued on 1/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 3/26/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 5/9/2022 | JEROME MAGAT PALMA |
| Issued | 5/13/2022 | APPLICANT |
| Building Plans Picked Up | 5/13/2022 | APPLICANT |
| CofO in Progress | 12/31/2022 | DAVID ANDERSON |
| Permit Finaled | 1/17/2023 | MICHAEL SMITH |
| CofO Issued | 1/17/2023 | MICHAEL SMITH |
| Permit Finaled | 1/17/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| ZA Case | Cleared | 4/1/2022 | LOUIS ORTEGA |
| Address approval | Cleared | 4/2/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 4/2/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2022 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 5/9/2022 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/1/2022 | Approved | DAVID ANDERSON |
| Pre-Inspection | 11/10/2022 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 11/17/2022 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 11/22/2022 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2022 | Approved | DAVID ANDERSON |
| Green Building Rough | 11/22/2022 | Approved | DAVID ANDERSON |
| Insulation | 11/22/2022 | Approved | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 11/22/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 11/28/2022 | Approved | DAVID ANDERSON |
| Final | 12/22/2022 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 12/22/2022 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 12/22/2022 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 12/22/2022 | Corrections Issued | DAVID ANDERSON |
| Final | 12/30/2022 | OK to Issue CofO | DAVID ANDERSON |
| Smoke Detectors | 12/30/2022 | Approved | DAVID ANDERSON |