15094 W BLEDSOE ST 91342
Certificate Information: 15094 W BLEDSOE ST 91342
- Application / Permit
- 22016-20000-08310
- Plan Check / Job No.
- B22VN03980
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- T. I. WITHIN (E) OFFICE/WAREHOUSE AND RE-STRIPE PARKING ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 8/10/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | SEWADA ZADOORIAN MILAGARDI |
| Disabled Access Plans Picked Up | 4/1/2022 | APPLICANT |
| Green Plans Picked Up | 4/1/2022 | APPLICANT |
| Corrections Issued | 4/5/2022 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 4/15/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/20/2022 | APPLICANT |
| Applicant returned to address corrections | 5/19/2022 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 7/18/2022 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 7/28/2022 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 8/10/2022 | SEWADA ZADOORAN MILAGARDI |
| Issued | 8/10/2022 | APPLICANT |
| CofO in Progress | 6/28/2023 | ANDREW DORSO |
| CofO Issued | 6/29/2023 | JEFFREY DURAN |
| Permit Finaled | 6/29/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 4/18/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 4/18/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 4/18/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2022 | DAGOVERTO GUERRERO |
| Green Code | Cleared | 5/12/2022 | MICHAEL AYERS |
| DAS Clearance | Cleared | 7/12/2022 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Architect | Beauchamp,, Daniel W; Lic. No.: C14593 | 16 EL CORAZON RANCHO SANTA MARGARITA, CA 92688 |
| Contractor | Xebec Building Company Inc; Lic. No.: 600621-B | 3020 OLD RANCH PARKWAY STE 200 SEAL BEACH, CA 90740 |
| Engineer | Gerges,, Rafik; Lic. No.: S5092 | 1906 W GARVEY AVE STE 200 WEST COVINA, CA 91790 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 9/16/2022 | Partial Approval | ANDREW DORSO |
| Green Building Rough | 9/16/2022 | Not Ready for Inspection | ANDREW DORSO |
| Drywall Nailing | 9/27/2022 | Partial Inspection | ANDREW DORSO |
| Green Building Rough | 9/27/2022 | Not Ready for Inspection | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2022 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 10/13/2022 | Partial Inspection | ANDREW DORSO |
| Deputy Drilled-In Anchors | 10/18/2022 | Approved | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 10/18/2022 | Partial Inspection | ANDREW DORSO |
| Insulation | 11/8/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 11/21/2022 | Partial Inspection | ANDREW DORSO |
| Green Building Rough | 11/21/2022 | Approved | ANDREW DORSO |
| Light Gage Steel Frame | 11/21/2022 | Partial Inspection | ANDREW DORSO |
| Insulation | 11/30/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 12/6/2022 | Partial Inspection | ANDREW DORSO |
| Insulation | 12/12/2022 | Approved | ANDREW DORSO |
| Special/Order Compliance | 12/12/2022 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 12/14/2022 | Partial Inspection | ANDREW DORSO |
| Deputy Steel/Welding | 12/15/2022 | Conditional Approval | ANDREW DORSO |
| Drywall Nailing | 12/21/2022 | Partial Inspection | ANDREW DORSO |
| Deputy Steel/Welding | 1/9/2023 | Conditional Approval | ANDREW DORSO |
| T-Bar Ceiling | 1/30/2023 | Corrections Issued | ANDREW DORSO |
| Deputy Reinf. Concrete | 2/1/2023 | Conditional Approval | ANDREW DORSO |
| Reinforced Masonry Frame | 2/1/2023 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Masonry | 2/6/2023 | Conditional Approval | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 2/6/2023 | Not Ready for Inspection | ANDREW DORSO |
| Masonry Wall/Backfill | 2/6/2023 | Not Ready for Inspection | ANDREW DORSO |
| Deputy Reinf. Masonry | 2/8/2023 | Conditional Approval | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 2/8/2023 | Partial Inspection | ANDREW DORSO |
| Masonry Wall/Backfill | 2/8/2023 | Partial Inspection | ANDREW DORSO |
| Reinforced Masonry Frame | 2/8/2023 | Partial Inspection | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 2/10/2023 | Approved | ANDREW DORSO |
| Masonry Wall/Backfill | 2/10/2023 | Approved | ANDREW DORSO |
| Reinforced Masonry Frame | 2/10/2023 | Approved | ANDREW DORSO |
| Special/Order Compliance | 2/10/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 3/1/2023 | Approved | ANDREW DORSO |
| Special/Order Compliance | 3/1/2023 | Approved | BRIAN KELLY |
| Drywall Nailing | 3/20/2023 | Approved | ANDREW DORSO |
| Insulation | 3/20/2023 | Approved | ANDREW DORSO |
| T-Bar Ceiling | 3/31/2023 | Approved | ANDREW DORSO |
| Final | 6/16/2023 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Final | 6/16/2023 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Concrete Frame | 6/16/2023 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 6/16/2023 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 6/16/2023 | Not Ready for Inspection | BRIAN KELLY |
| Final | 6/22/2023 | Corrections Issued | ANDREW DORSO |
| Green Building Final | 6/22/2023 | Approved | ANDREW DORSO |
| Reinforced Concrete Frame | 6/22/2023 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 6/22/2023 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 6/22/2023 | Approved | ANDREW DORSO |
| Final | 6/28/2023 | OK to Issue CofO | ANDREW DORSO |