11453 N DANUBE AVE 91344
Certificate Information: 11453 N DANUBE AVE 91344
- Application / Permit
- 22016-20000-08116
- Plan Check / Job No.
- B22VN03864
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d)
- Permit Issued
- Issued on 4/25/2022
- Issuing Office
- Current Status
- CofO Issued on 10/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2022 | SERGIO MUNIZ |
| Corrections Issued | 3/20/2022 | SERGIO MUNIZ |
| Applicant returned to address corrections | 4/9/2022 | SERGIO MUNIZ |
| Plan Check Approved | 4/25/2022 | SERGIO MUNIZ |
| Issued | 4/25/2022 | APPLICANT |
| Building Plans Picked Up | 4/26/2022 | APPLICANT |
| CofO in Progress | 9/5/2022 | JENNIFER RABUCHIN |
| No Progress | 9/19/2022 | ROBERT GOLD |
| CofO in Progress | 9/19/2022 | ROBERT GOLD |
| Permit Finaled | 10/15/2022 | MICHAEL SMITH |
| CofO Issued | 10/15/2022 | MICHAEL SMITH |
| Permit Finaled | 10/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/25/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 3/25/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2022 | ROMAN GUTIERREZ |
| Grading Pre-Inspection | Cleared | 4/4/2022 | VASIL MIHALEV |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/17/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Pre-Inspection | 5/17/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 5/26/2022 | Approved | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 5/27/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/13/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 6/13/2022 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 6/13/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 6/23/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 6/28/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 7/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 7/8/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/15/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 7/15/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 7/19/2022 | Approved | DEANDRE HOFFMAN |
| Green Building Rough | 7/19/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 7/19/2022 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Final | 8/12/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 8/12/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 8/12/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 8/12/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 8/12/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/12/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/12/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 8/12/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 8/25/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 8/25/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 8/25/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 8/25/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 9/2/2022 | Approved | JENNIFER RABUCHIN |
| Final | 9/2/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 9/2/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 9/2/2022 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 9/2/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |