1645 N VINE ST #903 90028
Certificate Information: 1645 N VINE ST #903 90028
- Application / Permit
- 22016-20000-07237
- Plan Check / Job No.
- B22VN03778
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- INTERIOR REMODEL TO (E) CONDOMINIUM BUILDING TO COMBINE UNITS #903 & #904. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 8/26/2022
- Issuing Office
- Current Status
- CofO Issued on 6/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 3/19/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 5/1/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 5/25/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 8/12/2022 | SAMUEL GONZALEZ |
| Issued | 8/26/2022 | APPLICANT |
| Building Plans Picked Up | 8/30/2022 | APPLICANT |
| CofO in Progress | 4/25/2024 | TIMOTHY POWELL |
| Permit Finaled | 6/26/2024 | RAFAEL ESPINOZA |
| CofO Issued | 6/26/2024 | RAFAEL ESPINOZA |
| Permit Finaled | 6/26/2024 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Address approval | Cleared | 4/4/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/5/2022 | JEANETTE VONG |
| "D" conditions | Cleared | 4/11/2022 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 4/11/2022 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 4/11/2022 | MIGUEL GAMBOA |
| Sign District | Cleared | 4/11/2022 | MIGUEL GAMBOA |
| Sign District | Cleared | 4/11/2022 | MIGUEL GAMBOA |
| ZA Case | Cleared | 4/11/2022 | MIGUEL GAMBOA |
| ZA Case | Cleared | 4/11/2022 | MIGUEL GAMBOA |
| ZA Case | Cleared | 4/11/2022 | MIGUEL GAMBOA |
| ZI | Cleared | 4/11/2022 | MIGUEL GAMBOA |
| ZI | Cleared | 4/11/2022 | MIGUEL GAMBOA |
| City Hist. Cultural Monument | Cleared | 4/12/2022 | LAMBERT GIESSINGER |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2022 | JEANETTE VONG |
| Redevelopment Project Area | Cleared | 4/19/2022 | GRACIELA ACOSTA |
| Demo/Removal of Rental Units | Cleared | 7/28/2022 | MICHELLE MATHEWS |
| Tenant Habitability Plan | Cleared | 7/29/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 10/27/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Light Gage Steel Frame | 2/17/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 2/21/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Special/Order Compliance | 2/27/2023 | Corrections Issued | TIMOTHY POWELL |
| Light Gage Steel Frame | 4/3/2023 | Approved | RONALD JIMENEZ |
| Pre-Inspection | 4/3/2023 | Approved | RONALD JIMENEZ |
| Drywall Nailing | 4/20/2023 | Approved | MARTIN TAVITIAN |
| Pre-Inspection | 2/8/2024 | Partial Inspection | TIMOTHY POWELL |
| Final | 4/24/2024 | OK to Issue CofO | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 4/24/2024 | SGSOV Approved | TIMOTHY POWELL |
| Smoke Detectors | 4/24/2024 | Approved | TIMOTHY POWELL |