431-431 1/2 W 58TH ST 90037
Certificate Information: 431-431 1/2 W 58TH ST 90037
- Application / Permit
- 22016-20000-07183
- Plan Check / Job No.
- B22VN03760
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ECPC: CONVERT A 17'-6" X 26"- 3" PORTION OF THE (E) DUPLEX INTO A (N) ATTACHED ACCESSORY DWELLING UNIT. PER LAMC 12.22 A.33(c) AND (e). AND CONVERT (E) DINING ROOM WITHIN UNIT #1 431 W 58TH ST INTO A (N) BEDROOM. ALL WORK PER WFPP
- Permit Issued
- Issued on 6/2/2022
- Issuing Office
- Current Status
- CofO Issued on 8/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 3/22/2022 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 5/23/2022 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 5/26/2022 | LUISANGEL VALENZUELA |
| Issued | 6/2/2022 | APPLICANT |
| Building Plans Picked Up | 7/15/2022 | APPLICANT |
| CofO in Progress | 8/4/2023 | SABAS ALONSO |
| Permit Finaled | 8/8/2023 | DEROLD HAUFF |
| CofO Issued | 8/8/2023 | DEROLD HAUFF |
| Permit Finaled | 8/8/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 3/24/2022 | LAUREN PADICK |
| Address approval | Cleared | 3/29/2022 | JEANIE LAM |
| Sewer availability | Cleared | 3/29/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2022 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/15/2022 | Not Ready for Inspection | SABAS ALONSO |
| Final | 7/15/2022 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 7/15/2022 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 7/15/2022 | Not Ready for Inspection | SABAS ALONSO |
| MERV13>=Final | 7/15/2022 | Not Ready for Inspection | SABAS ALONSO |
| MERV13>=Rough | 7/15/2022 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 7/15/2022 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 7/15/2022 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 7/21/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 7/21/2022 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| Final | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| MERV13>=Final | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| MERV13>=Rough | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 7/28/2022 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| Drywall Nailing | 8/2/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 8/2/2022 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 8/2/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 8/9/2022 | No Access for Inspection | SABAS ALONSO |
| Wood Frame | 8/9/2022 | No Access for Inspection | SABAS ALONSO |
| Drywall Nailing | 8/10/2022 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 8/10/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/29/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 8/29/2022 | Approved | SABAS ALONSO |
| Insulation | 8/29/2022 | Approved | SABAS ALONSO |
| MERV13>=Rough | 8/29/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/2/2022 | Not Ready for Inspection | ANDREW BEELI |
| Drywall Nailing | 9/2/2022 | Approved | ANDREW BEELI |
| Final | 9/2/2022 | Not Ready for Inspection | ANDREW BEELI |
| Green Building Final | 9/2/2022 | Not Ready for Inspection | ANDREW BEELI |
| Green Building Rough | 9/2/2022 | Not Ready for Inspection | ANDREW BEELI |
| MERV13>=Final | 9/2/2022 | Not Ready for Inspection | ANDREW BEELI |
| MERV13>=Rough | 9/2/2022 | Not Ready for Inspection | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 9/2/2022 | SGSOV Not Ready | ANDREW BEELI |
| Smoke Detectors | 9/2/2022 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Final | 9/7/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/15/2022 | Approved | SABAS ALONSO |
| Final | 9/15/2022 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 9/15/2022 | Approved | SABAS ALONSO |
| PLUMBING-Final | 9/15/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/20/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 9/20/2022 | Approved | SABAS ALONSO |
| Final | 9/20/2022 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 9/20/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 9/20/2022 | Approved | SABAS ALONSO |
| HVAC-Final | 9/20/2022 | Approved | SABAS ALONSO |
| MERV13>=Final | 9/20/2022 | Approved | SABAS ALONSO |
| MERV13>=Rough | 9/20/2022 | Approved | SABAS ALONSO |
| PLUMBING-Final | 9/20/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/20/2022 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 9/20/2022 | Approved | SABAS ALONSO |
| Final | 10/19/2022 | Not Ready for Inspection | SABAS ALONSO |
| Final | 6/5/2023 | Corrections Issued | SABAS ALONSO |
| Final | 8/3/2023 | OK to Issue CofO | SABAS ALONSO |