7672-7674 N PENFIELD AVE 91306

Certificate Information: 7672-7674 N PENFIELD AVE 91306

Application / Permit
22016-20000-06954
Plan Check / Job No.
B22VN03663
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE INTO JUNIOR ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(A) AND 65852.22. WORK PER ENGINEER.
Permit Issued
Issued on 7/27/2022
Issuing Office
Valley
Current Status
CofO Issued on 10/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2022 APPLICANT
Assigned to Plan Check Engineer 3/16/2022 ROSENDO MEDINA
Corrections Issued 3/19/2022 ROSENDO MEDINA
Applicant returned to address corrections 5/7/2022 ROSENDO MEDINA
Building Plans Picked Up 6/28/2022 APPLICANT
Applicant returned to address corrections 7/13/2022 LUISANGEL VALENZUELA
Issued 7/27/2022 APPLICANT
CofO in Progress 10/11/2022 VINCENT HANLEY
Permit Finaled 10/12/2022 JOHN JANSON
CofO Issued 10/12/2022 JOHN JANSON
Permit Finaled 10/12/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/1/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 4/1/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 4/4/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Your Favorite Contractor Inc; Lic. No.: 851344-B 18375 VENTURA BLVD #402      TARZANA, CA 91356
Engineer Kaballo,, Amir; Lic. No.: C90707 152 S SWALL DR      BEVERLY HILLS, CA 90211

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/5/2022 Partial Approval STEVEN BACK
Sewer 8/5/2022 Approved STEVEN BACK
Deputy Drilled-In Anchors 8/8/2022 Conditional Approval STEVEN BACK
Footing/Foundation/Slab 8/10/2022 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 8/18/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 8/18/2022 Partial Approval STEVEN BACK
PLUMBING-Rough 8/18/2022 Approved STEVEN BACK
Shower Pan 8/18/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 8/22/2022 Approved STEVEN BACK
Green Building Rough 8/22/2022 Approved STEVEN BACK
HVAC-Rough 8/22/2022 Approved STEVEN BACK
Insulation 8/22/2022 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 8/22/2022 Approved STEVEN BACK
Drywall Nailing 8/26/2022 Approved STEVEN BACK
Insulation 8/26/2022 Approved STEVEN BACK
ELECTRICAL-Final 10/7/2022 Approved VINCENT HANLEY
Final 10/7/2022 OK to Issue CofO VINCENT HANLEY
Green Building Final 10/7/2022 Approved VINCENT HANLEY
HVAC-Final 10/7/2022 Approved VINCENT HANLEY
PLUMBING-Final 10/7/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 10/7/2022 SGSOV Approved VINCENT HANLEY
Smoke Detectors 10/7/2022 Approved VINCENT HANLEY