2938 S SELBY AVE 90064

Certificate Information: 2938 S SELBY AVE 90064

Application / Permit
22016-20000-06941
Plan Check / Job No.
B22VN03654
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 360 SQ. FT. GARAGE AND THE 200 SQ. FT. TOOL SHED/ STORGAE INTO A (N) ACCESSORY DWELLING UNIT. IRR. SHAPE( 28'-0"X20'-0") PER 65852.2(e)(1)(A)
Permit Issued
Issued on 4/28/2022
Issuing Office
Current Status
CofO Issued on 9/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/11/2022 MOHAMMAD ESMAILI
Corrections Issued 3/12/2022 MOHAMMAD ESMAILI
Building Plans Picked Up 3/14/2022 APPLICANT
Plan Check Approved 4/28/2022 MOHAMMAD ESMAILI
Issued 4/28/2022 APPLICANT
CofO in Progress 9/23/2022 JOHNNY MIRANDA
Permit Finaled 9/24/2022 DANIEL ORRANTE
CofO Issued 9/24/2022 DANIEL ORRANTE
Permit Finaled 9/24/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/17/2022 JENSON LEE
Roof/Waste drainage to street Cleared 3/17/2022 JENSON LEE
Sewer availability Cleared 3/17/2022 JENSON LEE
Specific Plan Cleared 3/31/2022 LAUREN PADICK
ZI Cleared 3/31/2022 LAUREN PADICK
Eng Process Fee Ord 176,300 Cleared 4/2/2022 JOSE HERNANDEZ
Construction near power lines Cleared 4/19/2022 RIDWAN HARDY
GPI Written Notices Cleared 4/28/2022 MOHAMMAD ESMAILI
Grading Pre-Inspection Cleared 4/28/2022 MOHAMMAD ESMAILI

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Pearl Remodeling; Lic. No.: 955824-B 6803 YARMOUTH AVENUE      RESEDA, CA 91335

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/1/2022 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 6/2/2022 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 6/6/2022 Partial Approval KENNETH NAGLE
Underground Mechanical 6/10/2022 Corrections Issued JOHNNY MIRANDA
Underground Mechanical 6/14/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 7/1/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 7/1/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 7/6/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 7/12/2022 Partial Approval EVAN COOPER
Green Building Rough 7/12/2022 Not Ready for Inspection EVAN COOPER
HVAC-Rough 7/12/2022 Approved EVAN COOPER
MERV13>=Rough 7/12/2022 Not Ready for Inspection EVAN COOPER
Insulation 7/15/2022 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/15/2022 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/18/2022 Approved JOHNNY MIRANDA
Green Building Rough 7/18/2022 Approved JOHNNY MIRANDA
MERV13>=Rough 7/18/2022 Approved JOHNNY MIRANDA
Drywall Nailing 7/22/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/22/2022 Approved OGANES TARAKHCHYAN
Shower Pan 7/22/2022 Approved OGANES TARAKHCHYAN
Drywall Nailing 7/29/2022 Approved OGANES TARAKHCHYAN
Insulation 7/29/2022 Approved OGANES TARAKHCHYAN
Final 9/1/2022 Corrections Issued JOHNNY MIRANDA
Green Building Final 9/1/2022 Approved JOHNNY MIRANDA
MERV13>=Final 9/1/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 9/1/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 9/1/2022 Approved JOHNNY MIRANDA
Final 9/9/2022 Corrections Issued JOHNNY MIRANDA
Final 9/23/2022 OK to Issue CofO JOHNNY MIRANDA