7536 N KRAFT AVE 91605
Certificate Information: 7536 N KRAFT AVE 91605
- Application / Permit
- 22016-20000-06936
- Plan Check / Job No.
- B22VN03644
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ECPC: CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT. (20'-0"x32'-0") per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 4/25/2022
- Issuing Office
- Current Status
- CofO Issued on 1/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 3/11/2022 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 3/15/2022 | APPLICANT |
| Plan Check Approved | 3/24/2022 | MOHAMMAD ESMAILI |
| Issued | 4/25/2022 | APPLICANT |
| CofO in Progress | 11/9/2022 | JOHN HAYES |
| CofO Issued | 1/24/2023 | MICHAEL SMITH |
| Permit Finaled | 1/24/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/17/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | N E Construction; Lic. No.: 1042454-B | 6399 SMOKE TREE AVE OAK PARK, CA 91377 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/2/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/16/2022 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 5/16/2022 | Corrections Issued | CALEB MEISTER |
| Underground Mechanical | 5/16/2022 | Partial Approval | CALEB MEISTER |
| ELECTRICAL-Rough | 6/9/2022 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 6/9/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 6/9/2022 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 7/12/2022 | No Access for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/19/2022 | Approved | JOHN HAYES |
| Green Building Rough | 7/19/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 7/19/2022 | Approved | JOHN HAYES |
| Drywall Nailing | 7/25/2022 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 7/25/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 7/25/2022 | Approved | JOHN HAYES |
| Final | 9/6/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 9/6/2022 | No Access for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 9/6/2022 | No Access for Inspection | JOHN HAYES |
| Final | 9/21/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 9/21/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/21/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 9/21/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 9/30/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 9/30/2022 | No Access for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/30/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 9/30/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/27/2022 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Final | 11/9/2022 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 11/9/2022 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 11/9/2022 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 11/9/2022 | Approved | JOHN HAYES |