16331-16333 W CELTIC ST 91344

Certificate Information: 16331-16333 W CELTIC ST 91344

Application / Permit
22016-20000-06910
Plan Check / Job No.
B22VN03625
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EX ATT 18'X19'6" GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (e). ALL WORK PER WFPP
Permit Issued
Issued on 5/3/2022
Issuing Office
Current Status
CofO Issued on 1/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 HAYATO TSUCHIYA
Corrections Issued 3/22/2022 HAYATO TSUCHIYA
Plan Check Approved 5/2/2022 HAYATO TSUCHIYA
Issued 5/3/2022 APPLICANT
Building Plans Picked Up 5/5/2022 APPLICANT
CofO in Progress 12/29/2022 WILLIAM WREN
CofO in Progress 12/29/2022 WILLIAM WREN
CofO Issued 1/9/2023 RONALD MYRICK
Permit Finaled 1/9/2023 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 4/1/2022 JOHN LIN
Address approval Cleared 4/1/2022 JOHN LIN
Sewer availability Cleared 4/1/2022 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 4/8/2022 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/6/2022 No Access for Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 6/10/2022 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 7/5/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Partial Approval JAVIER RAMOS JR
Green Building Rough 8/4/2022 Not Ready for Inspection JAVIER RAMOS JR
MERV13>=Rough 8/4/2022 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 8/4/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 8/22/2022 Partial Approval DEANDRE HOFFMAN
BUILDING-Rough-Frame 8/30/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 8/30/2022 Approved JAVIER RAMOS JR
Insulation 8/30/2022 Partial Inspection JAVIER RAMOS JR
Sewer 8/30/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 9/9/2022 Approved JAVIER RAMOS JR
Green Building Rough 9/9/2022 Approved JAVIER RAMOS JR
HVAC-Rough 9/9/2022 Approved JAVIER RAMOS JR
Insulation 9/9/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 9/9/2022 Partial Approval JAVIER RAMOS JR
MERV13>=Rough 9/9/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 9/9/2022 Approved JAVIER RAMOS JR
Drywall Nailing 9/14/2022 Approved JAVIER RAMOS JR
Shower Pan 9/14/2022 Approved JAVIER RAMOS JR
Final 11/16/2022 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 11/16/2022 No Access for Inspection JAVIER RAMOS JR
MERV13>=Final 11/16/2022 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 11/16/2022 SGSOV Not Ready JAVIER RAMOS JR
Smoke Detectors 11/16/2022 Not Ready for Inspection JAVIER RAMOS JR
Final 12/14/2022 Corrections Issued JAVIER RAMOS JR
Green Building Final 12/14/2022 Approved JAVIER RAMOS JR
MERV13>=Final 12/14/2022 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/14/2022 SGSOV Not Ready JAVIER RAMOS JR
Smoke Detectors 12/14/2022 Approved JAVIER RAMOS JR
Final 12/28/2022 OK to Issue CofO WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 12/28/2022 SGSOV Approved WILLIAM WREN