16331-16333 W CELTIC ST 91344
Certificate Information: 16331-16333 W CELTIC ST 91344
- Application / Permit
- 22016-20000-06910
- Plan Check / Job No.
- B22VN03625
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EX ATT 18'X19'6" GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (e). ALL WORK PER WFPP
- Permit Issued
- Issued on 5/3/2022
- Issuing Office
- Current Status
- CofO Issued on 1/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | HAYATO TSUCHIYA |
| Corrections Issued | 3/22/2022 | HAYATO TSUCHIYA |
| Plan Check Approved | 5/2/2022 | HAYATO TSUCHIYA |
| Issued | 5/3/2022 | APPLICANT |
| Building Plans Picked Up | 5/5/2022 | APPLICANT |
| CofO in Progress | 12/29/2022 | WILLIAM WREN |
| CofO in Progress | 12/29/2022 | WILLIAM WREN |
| CofO Issued | 1/9/2023 | RONALD MYRICK |
| Permit Finaled | 1/9/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 4/1/2022 | JOHN LIN |
| Address approval | Cleared | 4/1/2022 | JOHN LIN |
| Sewer availability | Cleared | 4/1/2022 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2022 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/6/2022 | No Access for Inspection | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 6/10/2022 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 7/5/2022 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2022 | Partial Approval | JAVIER RAMOS JR |
| Green Building Rough | 8/4/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| MERV13>=Rough | 8/4/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/4/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 8/22/2022 | Partial Approval | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 8/30/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 8/30/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 8/30/2022 | Partial Inspection | JAVIER RAMOS JR |
| Sewer | 8/30/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/9/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 9/9/2022 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 9/9/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 9/9/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/9/2022 | Partial Approval | JAVIER RAMOS JR |
| MERV13>=Rough | 9/9/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/9/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 9/14/2022 | Approved | JAVIER RAMOS JR |
| Shower Pan | 9/14/2022 | Approved | JAVIER RAMOS JR |
| Final | 11/16/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 11/16/2022 | No Access for Inspection | JAVIER RAMOS JR |
| MERV13>=Final | 11/16/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 11/16/2022 | SGSOV Not Ready | JAVIER RAMOS JR |
| Smoke Detectors | 11/16/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 12/14/2022 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 12/14/2022 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 12/14/2022 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 12/14/2022 | SGSOV Not Ready | JAVIER RAMOS JR |
| Smoke Detectors | 12/14/2022 | Approved | JAVIER RAMOS JR |
| Final | 12/28/2022 | OK to Issue CofO | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 12/28/2022 | SGSOV Approved | WILLIAM WREN |