10252-10254 N ARLETA AVE 91331
Certificate Information: 10252-10254 N ARLETA AVE 91331
- Application / Permit
- 22016-20000-06891
- Plan Check / Job No.
- B22VN03610
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 12'-11" X 9'-7" PORTION OF (E) SINGLE FAMILY AND 23' X 18'-3" GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22 ALL WORK PER WFPP
- Permit Issued
- Issued on 10/11/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 4/13/2022 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 4/18/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/29/2022 | APPLICANT |
| Applicant returned to address corrections | 6/21/2022 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 9/8/2022 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 10/11/2022 | SEWADA ZADOORAN MILAGARDI |
| Issued | 10/11/2022 | APPLICANT |
| CofO in Progress | 7/5/2023 | JENNIFER RABUCHIN |
| CofO Issued | 7/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 6/2/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/2/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2022 | ROSE MARIE SMITH |
Contact Information
| Contractor | Valenzuela Pancho Construction; Lic. No.: 1067736-B | 544 ORANGE GROVE AVE SAN FERNANDO, CA 91340 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/22/2022 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 11/22/2022 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 11/22/2022 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/16/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/28/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/28/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/30/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 12/30/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| METHANE-Rough | 12/30/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/9/2023 | Approved | WILLIAM WREN |
| Green Building Rough | 1/9/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 1/9/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 1/10/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 1/13/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 1/18/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 1/18/2023 | Approved | WILLIAM WREN |
| Shower Pan | 1/18/2023 | Approved | WILLIAM WREN |
| Gas Test | 2/1/2023 | Partial Approval | JOHN COLEMAN |
| ELECTRICAL-Final | 7/6/2023 | Approved | JENNIFER RABUCHIN |
| Final | 7/6/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 7/6/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 7/6/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/6/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/6/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/6/2023 | Approved | JENNIFER RABUCHIN |