22261-22263 W MACFARLANE DR 91364
Certificate Information: 22261-22263 W MACFARLANE DR 91364
- Application / Permit
- 22016-20000-06876
- Plan Check / Job No.
- B22VN03602
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) 486 SQ. FT. GARAGE INTO A (N) ACCESSORY DWELLING UNIT. per GOV CODE 65852.2(e)(1)(A)
- Permit Issued
- Issued on 4/14/2022
- Issuing Office
- Current Status
- CofO Issued on 6/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 3/11/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 3/16/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 3/31/2022 | JEFFREY TANGONAN |
| Plan Check Approved | 4/1/2022 | JEFFREY TANGONAN |
| Building Plans Picked Up | 4/4/2022 | APPLICANT |
| Issued | 4/14/2022 | APPLICANT |
| CofO in Progress | 6/6/2023 | PETER FOLLING |
| Permit Finaled | 6/7/2023 | JOHN JANSON |
| Permit Finaled | 6/7/2023 | JOHN JANSON |
| CofO Issued | 6/7/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/17/2022 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 4/1/2022 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/18/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 4/26/2022 | Partial Approval | PETER FOLLING |
| Deputy Drilled-In Anchors | 5/2/2022 | No Access for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 5/3/2022 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2022 | Not Ready for Inspection | PETER FOLLING |
| Rough-Elec/Plmb/HVAC | 7/1/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 7/14/2022 | Approved | PETER FOLLING |
| Green Building Rough | 7/14/2022 | Approved | PETER FOLLING |
| Insulation | 7/14/2022 | Approved | PETER FOLLING |
| MERV13>=Rough | 7/14/2022 | Approved | PETER FOLLING |
| Drywall Nailing | 7/26/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 7/26/2022 | Partial Approval | MORRIS JACKSON |
| Interior/Exterior Lathing | 8/31/2022 | Approved | MORRIS JACKSON |
| Final | 5/11/2023 | Corrections Issued | PETER FOLLING |
| Green Building Final | 5/11/2023 | Approved | PETER FOLLING |
| MERV13>=Final | 5/11/2023 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 5/11/2023 | SGSOV Not Ready | PETER FOLLING |
| Smoke Detectors | 5/11/2023 | Approved | PETER FOLLING |
| Final | 6/5/2023 | OK to Issue CofO | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 6/5/2023 | SGSOV Approved | PETER FOLLING |
| Service/Power Release | 6/5/2023 | Approved | PETER FOLLING |