13161 W MINDANAO WAY 90292
Certificate Information: 13161 W MINDANAO WAY 90292
- Application / Permit
- 22016-20000-06811
- Plan Check / Job No.
- B22VN03577
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- No change of use and no exterior work. Interior work to include non-structural interior demo. New partitions, ceilings, doors, hardware, store fixtures, furniture and interior finishes.
- Permit Issued
- Issued on 7/29/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 11/29/2022
Permit Application Status History
| Submitted | 3/8/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 3/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | PETER MOSESIAN |
| Building Plans Picked Up | 4/11/2022 | APPLICANT |
| Green Plans Picked Up | 4/11/2022 | APPLICANT |
| Corrections Issued | 4/26/2022 | PETER MOSESIAN |
| Quality Review Completed | 4/26/2022 | OMID HEDAYAT |
| Plan Check Approved | 7/25/2022 | PETER MOSESIAN |
| Issued | 7/29/2022 | APPLICANT |
| Permit Finaled | 11/28/2022 | DAVID TSAU |
| CofO in Progress | 11/29/2022 | DAVID TSAU |
| No Progress | 11/29/2022 | DAVID TSAU |
Permit Application Clearance Information
| "Q" conditions | Cleared | 5/13/2022 | MIGUEL GAMBOA |
| DAS Clearance | Cleared | 6/28/2022 | NORLITO MEDRANO |
| Coastal Zone | Cleared | 7/12/2022 | MIGUEL GAMBOA |
| Green Code | Cleared | 7/13/2022 | MICHAEL AYERS |
| ZA Case | Cleared | 7/18/2022 | MIGUEL GAMBOA |
Contact Information
| Architect | Evernham,, Kevin T; Lic. No.: C32831 | 27413 N 22ND LANE PHOENIX, AZ 85085 |
| Contractor | Market Contractors Ltd; Lic. No.: 545305-B | 10250 NE MARX ST PORTLAND, OR 97220 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/15/2022 | Approved | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 9/27/2022 | Not Ready for Inspection | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 10/4/2022 | Approved | GRANT WOODS |
| Light Gage Steel Frame | 10/7/2022 | Partial Approval | GRANT WOODS |
| Light Gage Steel Frame | 10/11/2022 | Conditional Approval | GRANT WOODS |
| Drywall Nailing | 10/14/2022 | Approved | GRANT WOODS |
| Green Building Rough | 10/14/2022 | Approved | GRANT WOODS |
| T-Bar Ceiling | 11/10/2022 | Not Ready for Inspection | GRANT WOODS |
| T-Bar Ceiling | 11/14/2022 | Approved | GRANT WOODS |
| Final | 11/17/2022 | Conditional Approval | GRANT WOODS |
| Green Building Final | 11/17/2022 | Approved | GRANT WOODS |
| METHANE-Final | 11/17/2022 | Approved | GRANT WOODS |
| METHANE-Rough | 11/17/2022 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 11/17/2022 | Approved | GRANT WOODS |
| Wood Frame | 11/17/2022 | Approved | GRANT WOODS |
| Final | 11/22/2022 | Not Ready for Inspection | ALAN NOVAK |
| Final | 11/28/2022 | Permit Finaled | DAVID TSAU |
| Pre-Inspection | 11/28/2022 | Approved | DAVID TSAU |