8518 S FLIGHT AVE 90045
Certificate Information: 8518 S FLIGHT AVE 90045
- Application / Permit
- 22016-20000-06769
- Plan Check / Job No.
- B22VN03549
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 360 SQ. FT. DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT. PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/21/2022
- Issuing Office
- Current Status
- CofO Issued on 2/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 3/12/2022 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 3/14/2022 | APPLICANT |
| Plan Check Approved | 4/12/2022 | MOHAMMAD ESMAILI |
| Issued | 6/21/2022 | APPLICANT |
| CofO in Progress | 2/15/2023 | BOBBY KEY |
| Permit Finaled | 2/15/2023 | DANIEL ORRANTE |
| CofO Issued | 2/15/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/15/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/19/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 3/19/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2022 | JOSE HERNANDEZ |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Pearl Remodeling; Lic. No.: 955824-B | 6803 YARMOUTH AVENUE RESEDA, CA 91335 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/2/2022 | Partial Inspection | BOBBY KEY |
| Underground Mechanical | 9/9/2022 | Partial Approval | BOBBY KEY |
| Deputy Drilled-In Anchors | 9/15/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 9/15/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 11/2/2022 | Partial Approval | BOBBY KEY |
| Gas Test | 11/2/2022 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 11/2/2022 | Approved | BOBBY KEY |
| Insulation | 11/2/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 11/2/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 11/8/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 11/8/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2022 | Approved | BOBBY KEY |
| Green Building Rough | 11/10/2022 | Approved | BOBBY KEY |
| Insulation | 11/10/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 11/10/2022 | Partial Approval | BOBBY KEY |
| Drywall Nailing | 11/18/2022 | Approved | CLAYTON GRAHAM |
| Shower Pan | 11/18/2022 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Final | 2/2/2023 | Approved | BOBBY KEY |
| Final | 2/2/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 2/2/2023 | Approved | BOBBY KEY |
| HVAC-Final | 2/2/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 2/2/2023 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 2/2/2023 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 2/2/2023 | Approved | BOBBY KEY |
| Final | 2/10/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 2/10/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 2/10/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 2/10/2023 | SGSOV Approved | BOBBY KEY |
| Final | 2/15/2023 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 2/15/2023 | Approved | BOBBY KEY |