5804 N FIGUEROA ST 90042
Certificate Information: 5804 N FIGUEROA ST 90042
- Application / Permit
- 22016-20000-06571
- Plan Check / Job No.
- B22VN03462
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- TENANT IMPROVMENT TO THE (E) RETAIL SPACE. NO CHANGE TO OCCUPANCY. NO CHANGE TO PARKING.
- Permit Issued
- Issued on 7/11/2022
- Issuing Office
- Metro
- Current Status
- Issued on 7/11/2022
Permit Application Status History
| Submitted | 3/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2022 | SERGIO MUNIZ |
| Corrections Issued | 3/13/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 3/16/2022 | APPLICANT |
| Plan Check Approved | 6/29/2022 | SERGIO MUNIZ |
| Issued | 7/11/2022 | APPLICANT |
Permit Application Clearance Information
| HPOZ | Cleared | 3/25/2022 | KATIE DEBIASE |
| Specific Plan | Cleared | 4/7/2022 | DANIEL CORONADO |
Contact Information
| Architect | Paluch,, William L; Lic. No.: C28127 | 5532 N 40TH STREET PARADISE VALLEY, AZ 85253 |
| Contractor | Hughes - Nelson Painting Inc; Lic. No.: 467624-C33 | 720 INDIGO COURT POMONA, CA 917672262 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 8/10/2022 | Not Ready for Inspection | MARK FERRARI |
| Light Gage Steel Frame | 8/10/2022 | Not Ready for Inspection | MARK FERRARI |
| Light Gage Steel Frame | 8/15/2022 | Partial Approval | MARK FERRARI |
| Drywall Nailing | 8/19/2022 | Order to Comply Issued | MARK FERRARI |
| Drywall Nailing | 9/8/2022 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 9/8/2022 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 9/8/2022 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 9/9/2022 | Approved | DARRYL ARNOLD |
| T-Bar Ceiling | 9/16/2022 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 9/26/2022 | SGSOV Not Ready | MARK FERRARI |
| Final | 9/30/2022 | Corrections Issued | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/30/2022 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 9/30/2022 | Approved | MARK FERRARI |