7650-7652 W MACHREA ST 91042
Certificate Information: 7650-7652 W MACHREA ST 91042
- Application / Permit
- 22016-20000-06430
- Plan Check / Job No.
- B22VN03420
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT THE (E) SFD AND ATT. ONE CAR CARPORT INTO A (N) DUPLEX AND ATT. ONE CAR CARPORT
- Permit Issued
- Issued on 6/18/2022
- Issuing Office
- Current Status
- CofO Issued on 10/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 3/13/2022 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 3/14/2022 | APPLICANT |
| Applicant returned to address corrections | 3/23/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 4/20/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 5/16/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 6/18/2022 | MOHAMMAD ESMAILI |
| Issued | 6/18/2022 | APPLICANT |
| CofO in Progress | 9/21/2022 | MATTHEW NELSON |
| Permit Finaled | 10/15/2022 | MICHAEL SMITH |
| CofO Issued | 10/15/2022 | MICHAEL SMITH |
| Permit Finaled | 10/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/24/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/25/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/25/2022 | DAGOVERTO GUERRERO |
| Specific Plan | Cleared | 4/1/2022 | SARAH HOUNSELL |
| ZI | Cleared | 4/1/2022 | SARAH HOUNSELL |
| Hydrant and Access approval | Cleared | 4/27/2022 | DWIGHT SANKEY |
| Grading Pre-Inspection | Cleared | 5/18/2022 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 7/14/2022 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/2/2022 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/2/2022 | Approved | MATTHEW NELSON |
| HVAC-Rough | 8/2/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 8/2/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/4/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 8/11/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/16/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 9/13/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 9/13/2022 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 9/13/2022 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Final | 9/13/2022 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/13/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 9/13/2022 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Final | 9/20/2022 | Approved | MATTHEW NELSON |
| Final | 9/20/2022 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 9/20/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 9/20/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/20/2022 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 9/20/2022 | Approved | MATTHEW NELSON |