4601 S HOOVER ST 90037

Certificate Information: 4601 S HOOVER ST 90037

Application / Permit
22016-20000-06422
Plan Check / Job No.
B22VN03417
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 20'-3" x 56' ONE-STORY TO SINGLE FAMILY DWELLING; FIRE SPRINKLER SYSTEM IS REQUIRED
Permit Issued
Issued on 7/5/2022
Issuing Office
Current Status
CofO Issued on 11/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 SEAN SHAHMIRI
Corrections Issued 4/1/2022 SEAN SHAHMIRI
Quality Review Completed 4/11/2022 OMID HEDAYAT
Building Plans Picked Up 4/12/2022 APPLICANT
Applicant returned to address corrections 6/18/2022 SEAN SHAHMIRI
Applicant returned to address corrections 6/22/2022 SEAN SHAHMIRI
Plan Check Approved 6/30/2022 SEAN SHAHMIRI
Issued 7/5/2022 APPLICANT
CofO in Progress 11/8/2023 ALEJANDRO DE ARTOLA
Permit Finaled 11/21/2023 DEROLD HAUFF
CofO Issued 11/21/2023 DEROLD HAUFF
Permit Finaled 11/21/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/28/2022 STEVE MELGAR
Sewer availability Cleared 6/28/2022 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Sadjadi,, Abdulreza; Lic. No.: C51812 1223 WILSHIRE BLVD #169      SANTA MONICA, CA 90403

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Wood Construction 9/29/2022 Conditional Approval SABAS ALONSO
BUILDING-Rough-Frame 9/30/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 9/30/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/30/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 9/30/2022 Approved SABAS ALONSO
Green Building Rough 9/30/2022 Approved SABAS ALONSO
HVAC-Rough 9/30/2022 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 9/30/2022 Approved SABAS ALONSO
Sewer 9/30/2022 Approved SABAS ALONSO
Underground Mechanical 9/30/2022 Approved SABAS ALONSO
Insulation 10/5/2022 Approved RYAN SALAZAR
Drywall Nailing 10/24/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/24/2022 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 12/7/2022 Partial Approval ALEJANDRO DE ARTOLA
Shower Pan 12/7/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/27/2022 Approved ALEJANDRO DE ARTOLA
Final 12/27/2022 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 12/27/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Final 12/27/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 12/27/2022 Approved ALEJANDRO DE ARTOLA
Service/Power Release 12/27/2022 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 9/13/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/13/2023 SGSOV Approved SABAS ALONSO
Smoke Detectors 9/13/2023 Approved SABAS ALONSO
Final 10/25/2023 No Access for Inspection RONNIE MINDANAO
Final 11/8/2023 OK to Issue CofO ALEJANDRO DE ARTOLA
Service/Power Release 11/8/2023 Approved ALEJANDRO DE ARTOLA