4601 S HOOVER ST 90037
Certificate Information: 4601 S HOOVER ST 90037
- Application / Permit
- 22016-20000-06422
- Plan Check / Job No.
- B22VN03417
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 20'-3" x 56' ONE-STORY TO SINGLE FAMILY DWELLING; FIRE SPRINKLER SYSTEM IS REQUIRED
- Permit Issued
- Issued on 7/5/2022
- Issuing Office
- Current Status
- CofO Issued on 11/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | SEAN SHAHMIRI |
| Corrections Issued | 4/1/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 4/11/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/12/2022 | APPLICANT |
| Applicant returned to address corrections | 6/18/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 6/22/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 6/30/2022 | SEAN SHAHMIRI |
| Issued | 7/5/2022 | APPLICANT |
| CofO in Progress | 11/8/2023 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 11/21/2023 | DEROLD HAUFF |
| CofO Issued | 11/21/2023 | DEROLD HAUFF |
| Permit Finaled | 11/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 6/28/2022 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sadjadi,, Abdulreza; Lic. No.: C51812 | 1223 WILSHIRE BLVD #169 SANTA MONICA, CA 90403 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 9/29/2022 | Conditional Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/30/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 9/30/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 9/30/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 9/30/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 9/30/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 9/30/2022 | Approved | SABAS ALONSO |
| Sewer | 9/30/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 9/30/2022 | Approved | SABAS ALONSO |
| Insulation | 10/5/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 10/24/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/24/2022 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/7/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 12/7/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/27/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 12/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/27/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 9/13/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/13/2023 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 9/13/2023 | Approved | SABAS ALONSO |
| Final | 10/25/2023 | No Access for Inspection | RONNIE MINDANAO |
| Final | 11/8/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/8/2023 | Approved | ALEJANDRO DE ARTOLA |