5882 W 76TH ST 90045

Certificate Information: 5882 W 76TH ST 90045

Application / Permit
22016-20000-06420
Plan Check / Job No.
B22VN03415
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX 2ND FLR STORAGE ROOM (16'2"X20'2") OVER DET GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d). ALL WORK PER ENGR.
Permit Issued
Issued on 5/2/2022
Issuing Office
Current Status
CofO Issued on 7/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2022 APPLICANT
Assigned to Plan Check Engineer 3/11/2022 HAYATO TSUCHIYA
Corrections Issued 3/17/2022 HAYATO TSUCHIYA
Applicant returned to address corrections 4/14/2022 HAYATO TSUCHIYA
Plan Check Approved 4/25/2022 HAYATO TSUCHIYA
Building Plans Picked Up 4/25/2022 APPLICANT
Issued 5/2/2022 APPLICANT
CofO in Progress 7/21/2022 EVAN COOPER
Permit Finaled 7/27/2022 DANIEL ORRANTE
CofO Issued 7/27/2022 DANIEL ORRANTE
Permit Finaled 7/27/2022 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 3/30/2022 JENSON LEE
Sewer availability Cleared 3/30/2022 JENSON LEE
Specific Plan Cleared 3/30/2022 FREDDY GARCIA
Address approval Cleared 4/1/2022 DINAH GARIN
Construction near power lines Cleared 4/2/2022 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 4/4/2022 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/14/2022 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 6/14/2022 Approved BOBBY KEY
Green Building Rough 6/14/2022 Approved BOBBY KEY
PLUMBING-Rough 6/14/2022 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 6/15/2022 Approved BOBBY KEY
HVAC-Rough 6/15/2022 Approved BOBBY KEY
Insulation 6/15/2022 Approved BOBBY KEY
PLUMBING-Rough 6/15/2022 Approved BOBBY KEY
Sewer 6/15/2022 Approved BOBBY KEY
Drywall Nailing 6/20/2022 Approved RICHARD STEINBACH
Interior/Exterior Lathing 6/20/2022 Approved RICHARD STEINBACH
ELECTRICAL-Final 7/5/2022 Corrections Issued STEPHANIE SWANSON
Final 7/5/2022 Corrections Issued STEPHANIE SWANSON
Green Building Final 7/5/2022 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Final 7/5/2022 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 7/5/2022 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 7/5/2022 Approved STEPHANIE SWANSON
ELECTRICAL-Final 7/7/2022 Approved BOBBY KEY
Final 7/7/2022 Not Ready for Inspection BOBBY KEY
Green Building Final 7/7/2022 Approved BOBBY KEY
HVAC-Final 7/7/2022 Approved BOBBY KEY
Final 7/21/2022 OK to Issue CofO EVAN COOPER