7057 N HASKELL AVE #1-35 91406

Certificate Information: 7057 N HASKELL AVE #1-35 91406

Application / Permit
22016-20000-06346
Plan Check / Job No.
B22VN03350
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT (E) 17'-2" X 26'-2" REC ROOM AT 1ST FLOOR OF APARTMENT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/26/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2022 APPLICANT
Assigned to Plan Check Engineer 3/11/2022 RAPHAEL ROSAS
Corrections Issued 3/12/2022 RAPHAEL ROSAS
Applicant returned to address corrections 5/21/2022 RAPHAEL ROSAS
Plan Check Approved 5/27/2022 JESSE ARELLANO
Building Plans Picked Up 6/3/2022 APPLICANT
Issued 10/26/2022 APPLICANT
CofO in Progress 11/7/2023 STEVEN LEVITT
CofO in Progress 11/7/2023 STEVEN LEVITT
Permit Finaled 11/17/2023 JEFFREY DURAN
CofO Issued 11/17/2023 JEFFREY DURAN
Permit Finaled 11/17/2023 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 3/19/2022 CARLOS AGUILERA
Sewer availability Cleared 3/19/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/21/2022 CARLOS AGUILERA
"Q" conditions Cleared 4/4/2022 PABLO ESTRADA
Tract Map conditions Cleared 4/4/2022 PABLO ESTRADA
Miscellaneous Cleared 4/5/2022 ANDREW SANTIAGO
Tenant Habitability Plan Cleared 10/25/2022 ISMAEL HERNANDEZ

Contact Information

Contractor C W General Construction Inc; Lic. No.: 971704-B 1421 CALLE COLINA      THOUSAND OAKS, CA 91360
Engineer Hagopyan,, Edmond; Lic. No.: C80143 7939 WENTWORTH STREET      SUNLAND, CA 91040

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/22/2022 Not Ready for Inspection CAMERON CHABAN
Footing/Foundation/Slab 12/2/2022 Conditional Approval CAMERON CHABAN
Green Building Rough 12/2/2022 Not Ready for Inspection CAMERON CHABAN
Wood Frame 12/2/2022 Not Ready for Inspection CAMERON CHABAN
Green Building Rough 12/8/2022 Not Ready for Inspection CAMERON CHABAN
Wood Frame 12/8/2022 Not Ready for Inspection CAMERON CHABAN
Green Building Rough 1/10/2023 Not Ready for Inspection ANDREW DORSO
Special/Order Compliance 1/10/2023 Partial Inspection DEANDRE HOFFMAN
Wood Frame 1/10/2023 Partial Inspection ANDREW DORSO
Green Building Rough 1/12/2023 Approved CAMERON CHABAN
Insulation 1/12/2023 Approved CAMERON CHABAN
Wood Frame 1/12/2023 Conditional Approval CAMERON CHABAN
Drywall Nailing 1/25/2023 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 1/25/2023 Partial Approval DEANDRE HOFFMAN
Interior/Exterior Lathing 2/22/2023 Conditional Approval CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 5/26/2023 SGSOV Not Ready STEVEN LEVITT
SGSOV-Seismic Gas S/O Valve 5/30/2023 SGSOV Not Ready STEVEN LEVITT
Final 6/1/2023 OK to Issue CofO STEVEN LEVITT
Green Building Final 6/1/2023 Approved STEVEN LEVITT
SGSOV-Seismic Gas S/O Valve 6/1/2023 SGSOV Approved STEVEN LEVITT
Smoke Detectors 6/1/2023 Approved STEVEN LEVITT
Wood Frame 6/1/2023 Approved STEVEN LEVITT