10544 W CLARKSON ROAD 90064
Certificate Information: 10544 W CLARKSON ROAD 90064
- Application / Permit
- 22016-20000-06301
- Plan Check / Job No.
- B22VN03328
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE THE (E) 42 SQ. FT. REAR PORCH AND CONVERT IT TO A (N) LAUNDRY ROOM WITH AN INTERIOR REMODEL TO THE (E) KITCHEN.
- Permit Issued
- Issued on 4/7/2022
- Issuing Office
- Current Status
- Permit Finaled on 4/3/2024
Permit Application Status History
| Submitted | 3/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2022 | ANGELICA DAVE |
| Corrections Issued | 3/4/2022 | ANGELICA DAVE |
| Plan Check Approved | 3/31/2022 | ANGELICA MARTINEZ |
| Issued | 4/7/2022 | APPLICANT |
| Building Plans Picked Up | 4/8/2022 | APPLICANT |
| Permit Finaled | 4/2/2024 | OGANES TARAKHCHYAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/31/2022 | ANGELICA MARTINEZ |
Contact Information
| Contractor | Kempler & Company Incorporated; Lic. No.: 562533-B | 14731 SUTTON STREET SHERMAN OAKS, CA 91403 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/10/2022 | No Result Entered | RONALD WEBER |
| Excavation/Setback/Form/Re-Bar | 5/11/2022 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 5/11/2022 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2022 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 6/7/2022 | Corrections Issued | KENNETH NAGLE |
| Underground Mechanical | 6/7/2022 | Partial Approval | KENNETH NAGLE |
| Insulation | 6/13/2022 | Corrections Issued | KEVIN SARGSYAN |
| Gas Test | 6/22/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/22/2022 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 6/28/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 6/28/2022 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 6/28/2022 | Approved | KEVIN SARGSYAN |
| Insulation | 6/28/2022 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 6/28/2022 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 7/26/2022 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 7/26/2022 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 8/1/2022 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 4/2/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 4/2/2024 | Permit Finaled | OGANES TARAKHCHYAN |
| Green Building Final | 4/2/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 4/2/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 4/2/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/2/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 4/2/2024 | Approved | OGANES TARAKHCHYAN |