4113 S BUCKINGHAM ROAD 90008
Certificate Information: 4113 S BUCKINGHAM ROAD 90008
- Application / Permit
- 22016-20000-06289
- Plan Check / Job No.
- B22VN03318
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT (334 SQ FT) PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)1, (d)1, and (g)
- Permit Issued
- Issued on 5/11/2022
- Issuing Office
- Current Status
- CofO Issued on 11/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 4/3/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 5/10/2022 | JEROME MAGAT PALMA |
| Issued | 5/11/2022 | APPLICANT |
| Building Plans Picked Up | 5/16/2022 | APPLICANT |
| CofO in Progress | 11/18/2025 | LUIS CASTRO |
| Permit Finaled | 11/18/2025 | DEROLD HAUFF |
| CofO Issued | 11/18/2025 | DEROLD HAUFF |
| Permit Finaled | 11/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/11/2022 | WALLIE JONG |
| Sewer availability | Cleared | 4/11/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2022 | WALLIE JONG |
Contact Information
| Contractor | Lefert Maintenance Group Inc; Lic. No.: 1051028-B | 3325 WILSHIRE BOULEVARD #350 LOS ANGELES, CA 90010 |
| Engineer | Manlangit,, Vicente Balingasa; Lic. No.: C75499 | 7919 SAUSALITO AVE WEST HILLS, CA 91304 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 10/26/2022 | Approved | ANTHONY EGSON |
| Underground Mechanical | 10/26/2022 | Approved | ANTHONY EGSON |
| Underground Mechanical | 11/10/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/16/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/16/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 11/16/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 11/16/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 11/16/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/22/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 11/22/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 11/22/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 12/7/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 12/12/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/15/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 12/15/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 12/19/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/6/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 1/6/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 2/23/2023 | SGSOV Not Ready | ANTHONY EGSON |
| ELECTRICAL-Final | 4/13/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 4/13/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 4/13/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 4/13/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 4/13/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/13/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 4/13/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 4/26/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 4/26/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 4/26/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 4/26/2023 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/26/2023 | SGSOV Approved | ANTHONY EGSON |
| Final | 5/24/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 6/9/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 7/3/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 10/27/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Final | 10/28/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 10/28/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Final | 10/28/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 11/12/2025 | Approved | LUIS CASTRO |
| Final | 11/12/2025 | OK to Issue CofO | LUIS CASTRO |
| HVAC-Final | 11/12/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 11/12/2025 | Approved | LUIS CASTRO |