15736-15738 W DRELL ST 91342

Certificate Information: 15736-15738 W DRELL ST 91342

Application / Permit
22016-20000-06096
Plan Check / Job No.
B22VN03212
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 5/20/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 JESSE ARELLANO
Corrections Issued 3/10/2022 JESSE ARELLANO
Applicant returned to address corrections 4/16/2022 JESSE ARELLANO
Plan Check Approved 5/4/2022 JESSE ARELLANO
Building Plans Picked Up 5/6/2022 APPLICANT
Issued 5/20/2022 APPLICANT
CofO in Progress 11/2/2022 ARAM AVEDISIAN
CofO Issued 11/12/2022 MICHAEL SMITH
Permit Finaled 11/12/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/15/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/15/2022 CARLOS AGUILERA
Sewer availability Cleared 3/15/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/17/2022 CARLOS AGUILERA
Green Code Cleared 4/17/2022 JESSE ARELLANO
Grading Pre-Inspection Cleared 5/4/2022 JESSE ARELLANO

Contact Information

Contractor Ultimate Green Construction Inc; Lic. No.: 1023605-B 13302 FILMORE ST      PACOIMA, CA 91331

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/13/2022 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 6/23/2022 Approved HERBERT GIRON
Sewer 6/23/2022 Approved HERBERT GIRON
Underground Mechanical 6/23/2022 Approved HERBERT GIRON
BUILDING-Rough-Frame 7/12/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 7/12/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 7/18/2022 Approved ARAM AVEDISIAN
HVAC-Rough 7/18/2022 Approved ARAM AVEDISIAN
Wood Frame 7/18/2022 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/27/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 7/27/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 7/27/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 8/2/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 8/2/2022 Partial Approval ARAM AVEDISIAN
Sewer 9/21/2022 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 10/28/2022 Approved ARAM AVEDISIAN
Final 10/28/2022 Corrections Issued ARAM AVEDISIAN
Green Building Final 10/28/2022 Approved ARAM AVEDISIAN
Green Building Rough 10/28/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 10/28/2022 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 10/28/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Final 11/2/2022 Approved ARAM AVEDISIAN
Final 11/2/2022 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 11/2/2022 Approved ARAM AVEDISIAN
PLUMBING-Final 11/2/2022 Approved ARAM AVEDISIAN
Service/Power Release 11/2/2022 Approved ARAM AVEDISIAN