6165 N CANBY AVE 91335

Certificate Information: 6165 N CANBY AVE 91335

Application / Permit
22016-20000-05956
Plan Check / Job No.
B22VN03138
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 6/27/2022
Issuing Office
Current Status
CofO Issued on 3/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2022 APPLICANT
Assigned to Plan Check Engineer 3/4/2022 SERGIO MUNIZ
Corrections Issued 3/5/2022 SERGIO MUNIZ
Applicant returned to address corrections 5/19/2022 SERGIO MUNIZ
Applicant returned to address corrections 6/2/2022 SERGIO MUNIZ
Plan Check Approved 6/21/2022 SERGIO MUNIZ
Building Plans Picked Up 6/22/2022 APPLICANT
Issued 6/27/2022 APPLICANT
CofO in Progress 3/24/2023 SEAN HAUPT
Permit Finaled 3/31/2023 JOHN JANSON
CofO Issued 3/31/2023 JOHN JANSON
Permit Finaled 3/31/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/22/2022 CARLOS AGUILERA
Sewer availability Cleared 3/22/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/23/2022 CARLOS AGUILERA
Construction near power lines Cleared 5/4/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/4/2022 Approved SEAN HAUPT
Underground Mechanical 8/11/2022 Partial Approval SEAN HAUPT
Underground Mechanical 8/19/2022 Approved SEAN HAUPT
Pre-Inspection 8/25/2022 Approved SEAN HAUPT
Deputy Drilled-In Anchors 8/26/2022 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 8/30/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 9/22/2022 Not Ready for Inspection SEAN HAUPT
Green Building Rough 9/22/2022 Not Ready for Inspection SEAN HAUPT
Wood Frame 9/22/2022 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 10/25/2022 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 10/25/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 10/25/2022 Approved SEAN HAUPT
HVAC-Rough 10/25/2022 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 10/25/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 10/28/2022 Approved SEAN HAUPT
Green Building Rough 10/28/2022 Approved SEAN HAUPT
HVAC-Rough 10/28/2022 Approved SEAN HAUPT
Shower Pan 10/28/2022 Approved SEAN HAUPT
Insulation 11/17/2022 Approved SEAN HAUPT
Drywall Nailing 12/8/2022 Corrections Issued JON MCHUGH
Drywall Nailing 12/14/2022 Approved JON MCHUGH
Interior/Exterior Lathing 12/14/2022 Approved JON MCHUGH
ELECTRICAL-Rough 12/23/2022 Approved JON MCHUGH
Final 3/14/2023 Corrections Issued JON MCHUGH
Green Building Final 3/14/2023 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 3/14/2023 SGSOV Not Ready JON MCHUGH
Smoke Detectors 3/14/2023 Approved JON MCHUGH
Final 3/20/2023 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 3/20/2023 SGSOV Approved JON MCHUGH
Special/Order Compliance 3/20/2023 Partial Inspection SEAN WIRCH
Final 3/24/2023 OK to Issue CofO SEAN HAUPT