11040 N HASKELL AVE 91344

Certificate Information: 11040 N HASKELL AVE 91344

Application / Permit
22016-20000-05888
Plan Check / Job No.
B22VN03083
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN Conversion of the existing garage into an ADU per ordinance.
Permit Issued
Issued on 5/25/2022
Issuing Office
Current Status
CofO Issued on 5/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2022 APPLICANT
Assigned to Plan Check Engineer 3/1/2022 MICHAEL LOPEZ
Corrections Issued 3/1/2022 MICHAEL LOPEZ
Applicant returned to address corrections 3/10/2022 MICHAEL LOPEZ
Applicant returned to address corrections 4/8/2022 MICHAEL LOPEZ
Plan Check Approved 5/10/2022 MICHAEL LOPEZ
Issued 5/25/2022 APPLICANT
CofO in Progress 5/2/2023 JAVIER RAMOS JR
Permit Finaled 5/17/2023 MICHAEL SMITH
CofO Issued 5/17/2023 MICHAEL SMITH
Permit Finaled 5/17/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/7/2022 CARLOS AGUILERA
Sewer availability Cleared 3/7/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/8/2022 CARLOS AGUILERA

Contact Information

Architect Brumer,, Aaron Jason; Lic. No.: C30005 10999 RIVERSIDE DRIVE SUITE 300      STUDIO CITY, CA 91602
Contractor Cavalier Builders Inc; Lic. No.: 758563-B       ,
Engineer Pachunuri,, Nalin Kumar; Lic. No.: C78970 21126 INGOMAR CT      CANOGA PARK, CA 91304

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/8/2022 Conditional Approval JAVIER RAMOS JR
Footing/Foundation/Slab 8/16/2022 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 10/7/2022 Corrections Issued DEANDRE HOFFMAN
ELECTRICAL-Rough 10/7/2022 Corrections Issued DEANDRE HOFFMAN
PLUMBING-Rough 10/7/2022 Corrections Issued DEANDRE HOFFMAN
BUILDING-Rough-Frame 10/19/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 10/19/2022 Approved JAVIER RAMOS JR
Insulation 10/19/2022 Partial Approval JAVIER RAMOS JR
MERV13>=Rough 10/19/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 10/19/2022 Partial Approval JAVIER RAMOS JR
Underground Mechanical 10/19/2022 Corrections Issued JAVIER RAMOS JR
Drywall Nailing 10/27/2022 Approved JAVIER RAMOS JR
Green Building Rough 10/27/2022 Approved JAVIER RAMOS JR
HVAC-Rough 10/27/2022 Approved JAVIER RAMOS JR
Insulation 10/27/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 10/27/2022 Approved JAVIER RAMOS JR
Underground Mechanical 10/27/2022 Corrections Issued JAVIER RAMOS JR
Sewer 11/8/2022 Approved JAVIER RAMOS JR
Underground Mechanical 11/8/2022 Approved JAVIER RAMOS JR
Gas Test 12/7/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 1/9/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 1/9/2023 Not Ready for Inspection JAVIER RAMOS JR
Final 1/9/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 1/9/2023 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 1/9/2023 Approved JAVIER RAMOS JR
MERV13>=Final 1/9/2023 Approved JAVIER RAMOS JR
PLUMBING-Final 1/9/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 1/9/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 1/9/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 1/19/2023 Approved JAVIER RAMOS JR
Final 1/19/2023 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 1/19/2023 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 1/19/2023 Approved JAVIER RAMOS JR
PLUMBING-Final 1/19/2023 Approved JAVIER RAMOS JR
Final 5/1/2023 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 5/1/2023 Approved JAVIER RAMOS JR