5423 N KATHERINE AVE 91401

Certificate Information: 5423 N KATHERINE AVE 91401

Application / Permit
22016-20000-05856
Plan Check / Job No.
B22VN03068
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO THE EXISTING SINGLE FAMILY DWELLING AND CONVERSION OF ATTACHED PORCH TO EXPAND BATHROOM AND ENTRY - ALL WORK PER ENGINEERING*****COMPLY WITH DEPARTMENT ORDER effective date 01/18/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE*****
Permit Issued
Issued on 4/4/2022
Issuing Office
Current Status
Permit Finaled on 9/27/2023

Permit Application Status History

Submitted 2/28/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 DANIEL ABRAMYAN
Corrections Issued 3/5/2022 DANIEL ABRAMYAN
Plan Check Approved 4/4/2022 DANIEL ABRAMYAN
Issued 4/4/2022 APPLICANT
Building Plans Picked Up 4/4/2022 APPLICANT
Permit Finaled 9/26/2023 PATRICK LIEBREGT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JONATHAN FRANCHINI, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/5/2022 Approved GORDON ZUBER
Footing/Foundation/Slab 5/10/2022 Corrections Issued GORDON ZUBER
Reinforced Concrete Frame 5/10/2022 Not Ready for Inspection GORDON ZUBER
Wood Frame 5/10/2022 Not Ready for Inspection GORDON ZUBER
BUILDING-Rough-Frame 5/12/2022 Not Ready for Inspection GORDON ZUBER
Footing/Foundation/Slab 5/12/2022 Not Ready for Inspection GORDON ZUBER
Reinforced Concrete Frame 5/12/2022 Not Ready for Inspection GORDON ZUBER
BUILDING-Rough-Frame 5/17/2022 Corrections Issued GORDON ZUBER
Footing/Foundation/Slab 5/17/2022 Approved GORDON ZUBER
Reinforced Concrete Frame 5/17/2022 Approved GORDON ZUBER
ELECTRICAL-Rough 8/17/2022 Not Ready for Inspection GORDON ZUBER
Rough-Elec/Plmb/HVAC 8/17/2022 Not Ready for Inspection GORDON ZUBER
BUILDING-Rough-Frame 9/12/2022 Corrections Issued GORDON ZUBER
ELECTRICAL-Rough 9/12/2022 Approved GORDON ZUBER
HVAC-Rough 9/12/2022 Corrections Issued GORDON ZUBER
PLUMBING-Rough 9/12/2022 Approved GORDON ZUBER
HVAC-Rough 9/16/2022 Approved GORDON ZUBER
Wood Frame 9/16/2022 Approved GORDON ZUBER
BUILDING-Rough-Frame 10/3/2022 Approved GORDON ZUBER
Interior/Exterior Lathing 10/3/2022 Approved GORDON ZUBER
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Approved GORDON ZUBER
Gas Test 10/17/2022 Approved GORDON ZUBER
Insulation 10/17/2022 Approved GORDON ZUBER
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Approved GORDON ZUBER
Masonry Wall/Backfill 10/27/2022 Not Ready for Inspection GORDON ZUBER
PLUMBING-Final 10/27/2022 Not Ready for Inspection GORDON ZUBER
Shower Pan 10/27/2022 Approved GORDON ZUBER
Special/Order Compliance 10/27/2022 Approved GORDON ZUBER
Drywall Nailing 12/12/2022 Approved PATRICK LIEBREGT
Interior/Exterior Lathing 12/12/2022 Approved PATRICK LIEBREGT
Pre-Inspection 12/12/2022 Approved PATRICK LIEBREGT
ELECTRICAL-Final 2/15/2023 Not Ready for Inspection PATRICK LIEBREGT
Service/Power Release 2/16/2023 Approved PATRICK LIEBREGT
Final 9/26/2023 Permit Finaled PATRICK LIEBREGT
SGSOV-Seismic Gas S/O Valve 9/26/2023 SGSOV Approved PATRICK LIEBREGT
Smoke Detectors 9/26/2023 Approved PATRICK LIEBREGT