1878 S COMSTOCK AVE 90025

Certificate Information: 1878 S COMSTOCK AVE 90025

Application / Permit
22016-20000-05620
Plan Check / Job No.
B22VN02951
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/10/2022
Issuing Office
Current Status
Permit Finaled on 9/8/2023

Permit Application Status History

Submitted 2/25/2022 APPLICANT
Assigned to Plan Check Engineer 3/2/2022 RAPHAEL ROSAS
Corrections Issued 3/2/2022 RAPHAEL ROSAS
Applicant returned to address corrections 5/5/2022 RAPHAEL ROSAS
Applicant returned to address corrections 6/6/2022 RAPHAEL ROSAS
Plan Check Approved 7/1/2022 RAPHAEL ROSAS
Building Plans Picked Up 7/6/2022 APPLICANT
Issued 7/10/2022 APPLICANT
Permit Finaled 9/7/2023 CHRISTOPHER WILSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/25/2022 KIRK LINKLATER

Contact Information

Contractor Red Stag Construction Company; Lic. No.: 964664-B 9948 SEPULVEDA BLVD #6      MISSION HILLS, CA 91345
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/6/2022 Corrections Issued STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 9/7/2022 Approved MICHAEL PELHAM
Footing/Foundation/Slab 9/7/2022 Approved MICHAEL PELHAM
ELECTRICAL-Rough 11/4/2022 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 11/4/2022 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 11/4/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Wood Frame 11/4/2022 Corrections Issued OGANES TARAKHCHYAN
BUILDING-Rough-Frame 11/18/2022 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 11/18/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 11/22/2022 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Rough 11/22/2022 Not Ready for Inspection STEPHANIE SWANSON
ELECTRICAL-Rough 11/29/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 11/29/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 11/29/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 12/1/2022 Approved STEPHANIE SWANSON
HVAC-Rough 12/1/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 12/1/2022 Corrections Issued STEPHANIE SWANSON
Insulation 12/5/2022 Partial Approval STEPHANIE SWANSON
Shower Pan 12/5/2022 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 12/7/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 12/7/2022 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 12/7/2022 Approved STEPHANIE SWANSON
PLUMBING-Rough 12/7/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 12/8/2022 Partial Approval STEPHANIE SWANSON
Insulation 12/9/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 12/9/2022 Approved STEPHANIE SWANSON
Drywall Nailing 12/15/2022 Conditional Approval MICHAEL PELHAM
Green Building Final 12/15/2022 Corrections Issued MICHAEL PELHAM
HVAC-Rough 12/15/2022 Partial Approval MICHAEL PELHAM
BUILDING-Rough-Frame 8/9/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Final 8/9/2023 Corrections Issued STEPHANIE SWANSON
Final 8/9/2023 Corrections Issued STEPHANIE SWANSON
HVAC-Final 8/9/2023 Approved STEPHANIE SWANSON
METHANE-Rough 8/9/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 8/9/2023 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 8/9/2023 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 8/9/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Final 9/7/2023 Approved CHRISTOPHER WILSON
Final 9/7/2023 Permit Finaled CHRISTOPHER WILSON
Gas Test 9/7/2023 Approved CHRISTOPHER WILSON
PLUMBING-Final 9/7/2023 Approved CHRISTOPHER WILSON