899 N SAYRE LANE 90026

Certificate Information: 899 N SAYRE LANE 90026

Application / Permit
22016-20000-05578
Plan Check / Job No.
B22VN02927
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 28' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
Permit Issued
Issued on 5/5/2022
Issuing Office
Current Status
CofO Issued on 12/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 RAPHAEL ROSAS
Corrections Issued 3/6/2022 RAPHAEL ROSAS
Applicant returned to address corrections 4/12/2022 RAPHAEL ROSAS
Plan Check Approved 4/26/2022 RAPHAEL ROSAS
Building Plans Picked Up 4/29/2022 APPLICANT
Issued 5/5/2022 APPLICANT
CofO in Progress 11/29/2022 FREDDIE RIVERA
Permit Finaled 12/5/2022 DEROLD HAUFF
CofO Issued 12/5/2022 DEROLD HAUFF
Permit Finaled 12/5/2022 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 3/7/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 3/9/2022 STEVE MELGAR
Private street Cleared 3/24/2022 MIGUEL GAMBOA
Address approval Cleared 3/29/2022 STEVE MELGAR
Grading Pre-Inspection Cleared 4/13/2022 RAPHAEL ROSAS

Contact Information

Contractor Progressive Construction Inc; Lic. No.: 1024265-B 1522 16TH STREET      SANTA MONICA, CA 90404

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/10/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 5/10/2022 Partial Approval FREDDIE RIVERA
Deputy Drilled-In Anchors 5/11/2022 Conditional Approval JOSE AVILA
BUILDING-Rough-Frame 5/25/2022 Partial Approval FREDDIE RIVERA
Green Building Rough 5/25/2022 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 6/7/2022 Conditional Approval FREDDIE RIVERA
ELECTRICAL-Rough 6/7/2022 Approved FREDDIE RIVERA
Green Building Rough 6/7/2022 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 6/7/2022 Conditional Approval FREDDIE RIVERA
Interior/Exterior Lathing 6/23/2022 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 6/23/2022 Approved FREDDIE RIVERA
Insulation 6/29/2022 No Access for Inspection FREDDIE RIVERA
Interior/Exterior Lathing 6/29/2022 No Access for Inspection FREDDIE RIVERA
Shower Pan 6/29/2022 No Access for Inspection FREDDIE RIVERA
Insulation 7/5/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 7/5/2022 Approved FREDDIE RIVERA
Shower Pan 7/5/2022 Approved FREDDIE RIVERA
Drywall Nailing 7/8/2022 Approved FREDDIE RIVERA
Underground Mechanical 10/5/2022 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 10/18/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 10/18/2022 Approved FREDDIE RIVERA
Final 10/18/2022 Partial Inspection FREDDIE RIVERA
Green Building Final 10/18/2022 Partial Inspection FREDDIE RIVERA
Green Building Rough 10/18/2022 Approved FREDDIE RIVERA
HVAC-Final 10/18/2022 Conditional Approval FREDDIE RIVERA
PLUMBING-Final 10/18/2022 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/18/2022 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 10/18/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 11/28/2022 Approved FREDDIE RIVERA
Final 11/28/2022 OK to Issue CofO FREDDIE RIVERA
Green Building Final 11/28/2022 Approved FREDDIE RIVERA
HVAC-Final 11/28/2022 Approved FREDDIE RIVERA
PLUMBING-Final 11/28/2022 Approved FREDDIE RIVERA