756 E COLDEN AVE 90002

Certificate Information: 756 E COLDEN AVE 90002

Application / Permit
22016-20000-05516
Plan Check / Job No.
B22VN02908
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-4" X 20' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/15/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 RAPHAEL ROSAS
Corrections Issued 3/5/2022 RAPHAEL ROSAS
Plan Check Approved 4/21/2022 RAPHAEL ROSAS
Building Plans Picked Up 4/26/2022 APPLICANT
Issued 6/15/2022 APPLICANT
CofO in Progress 3/21/2024 BEN MOLSTAD
Permit Finaled 3/28/2024 ANSON MAGLASANG
Permit Finaled 3/28/2024 ANSON MAGLASANG
CofO Issued 3/28/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 3/15/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 3/17/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 4/8/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Owner-Builder       ,
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/20/2022 Approved JOHN KLARIN
Excavation/Setback/Form/Re-Bar 10/5/2022 Corrections Issued ALIZAH MAYAGOITIA
Deputy Drilled-In Anchors 10/7/2022 Conditional Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 10/13/2022 Approved ALIZAH MAYAGOITIA
Sewer 10/13/2022 Partial Approval ALIZAH MAYAGOITIA
Underground Mechanical 10/13/2022 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 10/17/2022 Partial Approval JOHN KLARIN
Footing/Foundation/Slab 10/18/2022 Approved JOHN KLARIN
PLUMBING-Rough 11/18/2022 Corrections Issued JOHN KLARIN
PLUMBING-Rough 11/21/2022 Approved JOHN KLARIN
Pre-Inspection 11/21/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 1/11/2023 Not Ready for Inspection JAMES CHAVEZ
Green Building Rough 1/11/2023 Not Ready for Inspection JAMES CHAVEZ
Pre-Inspection 1/11/2023 Approved JAMES CHAVEZ
Pre-Inspection 1/26/2023 Partial Approval JOHN KLARIN
Pre-Inspection 1/31/2023 Partial Approval JOHN KLARIN
Service/Power Release 1/31/2023 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 3/2/2023 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 3/2/2023 Approved JOHN KLARIN
Green Building Rough 3/2/2023 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 3/2/2023 Corrections Issued JOHN KLARIN
Gas Test 3/30/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 3/30/2023 Not Ready for Inspection JOHN KLARIN
Green Building Rough 6/5/2023 Approved JAMES CHAVEZ
Insulation 6/5/2023 Corrections Issued JAMES CHAVEZ
Insulation 6/6/2023 Corrections Issued JOHN KLARIN
Insulation 6/15/2023 Approved JOHN KLARIN
Drywall Nailing 7/18/2023 Approved JAMES CHAVEZ
Shower Pan 10/11/2023 Approved JOHN KLARIN
ELECTRICAL-Final 10/27/2023 Not Ready for Inspection JAMES CHAVEZ
BUILDING-Rough-Frame 2/9/2024 Approved BEN MOLSTAD
Final 2/9/2024 Corrections Issued BEN MOLSTAD
Green Building Final 2/9/2024 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 2/9/2024 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 2/9/2024 Corrections Issued BEN MOLSTAD
Final 2/23/2024 Corrections Issued BEN MOLSTAD
Green Building Final 2/23/2024 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Approved BEN MOLSTAD
Smoke Detectors 2/23/2024 Approved BEN MOLSTAD
ELECTRICAL-Final 3/20/2024 Approved BEN MOLSTAD
Final 3/20/2024 OK to Issue CofO BEN MOLSTAD
Green Building Final 3/20/2024 Approved BEN MOLSTAD
HVAC-Final 3/20/2024 Approved BEN MOLSTAD
PLUMBING-Final 3/20/2024 Approved BEN MOLSTAD
Service/Power Release 3/21/2024 Approved BEN MOLSTAD